Power Map · Operating

Meta Temple, Temple

Meta Temple is an SI data center in Temple, Texas, United States, owned by Meta and used by Meta. Epoch AI estimates its IT power at 178 MW as of September 30, 2026, with 3 buildings operating. Its public timeline starts on April 1, 2022.

IT power
178 MWSep 30, 2026
Facility power
231 MW
Status
Operating
Buildings operating
3

Where it is

The site and its facts

Meta Temple on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Temple, Texas, United StatesOpen in OpenStreetMap
Place
Temple, Texas, United States
Address
2310 Eberhardt Rd, Temple, TX 76504
Coordinates
31.1309° N, 97.3667° W
Owner
Meta
Users
Meta
Chips
B300
Compute
About 202,473 H100 equivalentsEpoch AI estimate, Sep 30, 2026
Builders
JE Dunn

Heat Watch

Meta Temple: heat seen from space

Over the last three summers NASA's MODIS read the ground here +0.5 °C against the land 5 to 10 km around it by day.

Lights On

Meta Temple: light at night

NASA's night imagery read 68.6 of 100 over this site in October 2026, against 43.5 in October 2018, the first month read. Against a year before: +0.9 points. The place was already bright at the first reading, so growth is harder to see. Light is not proof of what runs inside.

Timeline

Dated, from the public record

Epoch AI's dated notes on Meta Temple, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

  1. Land clearing begins.

    No IT power yet0 operating

  2. A traditional H-shaped Meta data center is partially built.

    No IT power yet0 operating

  3. The traditional Meta data center has been demolished mid-construction, in favor of Meta's new AI-optimized design.

    No IT power yet0 operating

  4. Building 1 and 2 look complete from outside, with all electrical and cooling equipment installed. Space is cleared for Building 3.

    No IT power yet0 operating

  5. Building 1 and 2 are operational. Activity related to the air quality permit (namely, emergency diesel generators) was reported to have started as of 2025-12-09. This is our best estimate, but note that the planned completion date in this regulatory filing is 2026-03-01.

    152 MW2 operating

  6. Building 3 is under construction. An outline is visible for the building which has similar dimensions to those deployed at the Meta Prometheus site.

    152 MW2 operating

  7. Building 3 is operational. Based on the stated completion date in this regulatory filing

    178 MW3 operating

Adopt a site

Watch Meta Temple

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

The watcher

Loading the watcher.

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

  • Approved updates show here with their date.

Sources

Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

Questions

Meta Temple, answered

Where it is, who owns it and how much power it uses, from the public record.

Where is Meta Temple?

Meta Temple is in Temple, Texas, United States, at 2310 Eberhardt Rd, Temple, TX 76504. Epoch AI publishes its coordinates as 31.1309, -97.3667.

Who owns Meta Temple?

Epoch AI lists Meta as its owner and Meta as its user.

How much power does Meta Temple use?

Epoch AI estimates its IT power at 178 MW as of September 30, 2026, and its total facility power at 231 MW.

Is Meta Temple operating?

Yes. Epoch AI counts 3 buildings operating as of September 30, 2026.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).