OpenAI Stargate Michigan, Benton

OpenAI Stargate Michigan is an SI data center in Benton, Michigan, United States, owned by Oracle and used by OpenAI. Epoch AI tracks it as under construction: no building is operating yet as of March 12, 2026, and projects 988 MW by December 31, 2028. Its public timeline starts on December 4, 2025.

IT power
Not statedEpoch AI
Facility power
Not stated
Status
Under construction
Buildings operating
0

Where it is

The site and its facts

OpenAI Stargate Michigan on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Benton, Michigan, United StatesOpen in OpenStreetMap
Place
Benton, Michigan, United States
Address
Not public
Coordinates
42.1212° N, 83.8842° W
Owner
Oracle
Users
OpenAI
Project
Stargate
Projected
988 MW IT power by December 31, 2028Epoch AI projection, not a fact yet

The Gigawatt Ledger · Under construction

Stargate Michigan: announced against built

1.38 GW was announced for this project. Epoch AI tracks the site as under construction, with no building operating as of March 12, 2026.

Heat Watch

OpenAI Stargate Michigan: heat seen from space

Over the last three summers NASA's MODIS read the ground here +0.8 °C against the land 5 to 10 km around it by day.

Lights On

OpenAI Stargate Michigan: light at night

NASA's night imagery read 21.9 of 100 over this site in October 2026, against 1.1 in October 2018, the first month read. Against a year before: +21.0 points. Light is not proof of what runs inside.

Timeline

Dated, from the public record

Epoch AI's dated notes on OpenAI Stargate Michigan, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

  1. Land clearing begins for the entire site

    No IT power yet0 operating

  2. Land clearing continues for all buildings (1-3)

    No IT power yet0 operating

  3. Groundwork is visible for Building 1, at the left end of the site.

    No IT power yet0 operating

  4. Buildings 1-3 operational. Based on when maximum power load will be provided by DTE energy (Dec 2027), which can be extended by a year. Source, page 3

    988 MW3 operating

Adopt a site

Watch OpenAI Stargate Michigan

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

The watcher

Loading the watcher.

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

  • Approved updates show here with their date.

Sources

Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

Questions

OpenAI Stargate Michigan, answered

Where it is, who owns it and how much power it uses, from the public record.

Where is OpenAI Stargate Michigan?

OpenAI Stargate Michigan is in Benton, Michigan, United States. Epoch AI publishes its coordinates as 42.1212, -83.8842.

Who owns OpenAI Stargate Michigan?

Epoch AI lists Oracle as its owner and OpenAI as its user.

How much power does OpenAI Stargate Michigan use?

No building is operating yet, so Epoch AI states no IT power for it today. It projects 988 MW of IT power by December 31, 2028.

Is OpenAI Stargate Michigan operating?

Not yet. Epoch AI tracks it as under construction, with no building operating on its latest entry.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).