Power Map · Operating, expanding
Anthropic-Amazon New Carlisle, New Carlisle
Anthropic-Amazon New Carlisle is an SI data center in New Carlisle, Indiana, United States, owned by Amazon and used by Anthropic. Epoch AI estimates its IT power at 1,037 MW as of October 19, 2026, with 18 buildings operating, and projects 1,925 MW by March 17, 2028. Its public timeline starts on February 9, 2024.
- IT power
- 1,037 MWOct 19, 2026
- Facility power
- 1,244 MW
- Status
- Operating, expanding
- Buildings operating
- 18
Where it is
The site and its facts
Anthropic-Amazon New Carlisle on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- New Carlisle, Indiana, United States
- Address
- 55001 Larrison Blvd, New Carlisle, IN 46552
- Coordinates
- 41.6794° N, 86.4712° W
- Owner
- Amazon
- Users
- Anthropic
- Project
- Project Rainier
- Chips
- Trainium2
- Compute
- About 818,428 H100 equivalentsEpoch AI estimate, Oct 19, 2026
- Projected
- 1,925 MW IT power by March 17, 2028Epoch AI projection, not a fact yet
Seen from orbit · Compute Watch
The newest clear pass over Anthropic-Amazon New Carlisle
The image loads from NASA's public imagery: true color at 30 m per pixel, about 5 km across, north up.
Open Compute WatchThe Gigawatt Ledger · Partly energized
Project Rainier, New Carlisle: announced against built
No power figure was announced for this project. No power figure was announced. Epoch AI estimates 1,037 MW of IT power in operation (1,244 MW for the whole facility) as of October 19, 2026, with more capacity on its timeline.
Heat Watch
Anthropic-Amazon New Carlisle: heat seen from space
Over the last three summers NASA's MODIS read the ground here +0.7 °C against the land 5 to 10 km around it by day.
Lights On
Anthropic-Amazon New Carlisle: light at night
NASA's night imagery read 59.5 of 100 over this site in October 2026, against 9.5 in October 2018, the first month read. Against a year before: +7.2 points. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on Anthropic-Amazon New Carlisle, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
Land clearing begins in the northern section
No IT power yet0 operating
Land clearing begins in the southern section
No IT power yet0 operating
Roof complete on building 11
No IT power yet0 operating
Buildings 1-7 are operational. Based on all of the roofs being completed for over 5 months.
398 MW7 operating
Roof complete on building 16. Generators are being installed for buildings 8-15. In the north, Building 17 and 18 are under construction. To the south of buildings 8-16, a concrete pad is visible, and an expanded car park next to it.
398 MW7 operating
Confirmation that nearly 500,000 chips are operational, which fits buildings 1-7. In an interview, AWS CEO says "they're already running...about 500,000 [Trainium2] chips in Indiana today".
398 MW7 operating
Buildings 8-11 are operational, given it's been over 7 months since their roofs were complete, and the backup generators and roof chimneys look complete. The roof is almost complete for Building 17 and 18.
626 MW11 operating
Buildings 12-16 still have a few generators that look incomplete, so they are unlikely to be operational just yet. Buildings 17-18 still have ongoing roof work, no generators. Just south of Buildings 9-16, the outlines of a site for Buildings 19-32 are taking shape.
626 MW11 operating
Buildings 12-16 are operational. Based on how long previous buildings took, when they were in a similar state to Buildings 12-16 in December.
910 MW16 operating
Buildings 17-18 fully roofed but still having surrounding generators/cooling under construction. Cleared land for buildings 19-32 is still bare, with no building foundations visible yet. Based on satellite imagery.
910 MW16 operating
Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to account for commissioning and adjacent cooling units not being complete yet.
1,037 MW18 operating
Buildings 19-32 are operational. This is an estimate based on how long Buildings 1-16 took to become operational. In May 2026, the foundation of several buildings and a substation was visible at the site of Buildings 19-32. Buildings 1-16 took 1 year and 10 months to go from a similar state to operational. So we add 1 year and 10 months to May 2026 to get this date estimate. The power capacity is based on an air quality permit filed in May 2026, and the compute capacity is based on Trainium3 chips.
1,925 MW32 operating
Adopt a site
Watch Anthropic-Amazon New Carlisle
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Air Construction Permit application for the northern portion
- Backup diesel generator referenced in the permit
- Announcement of Project Rainier coming online
- Air permit for Buildings 19-32, suggesting expansion to 2.3 GW total facility power
- Epoch AI, "AI data centers", the record for Anthropic-Amazon New Carlisle (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
139 km away
Google Fort Wayne
Fort Wayne, Indiana, United States
IT power not stated
163 km away
Microsoft Fairwater Wisconsin
Mount Pleasant, Wisconsin, United States
369 MW IT power
220 km away
OpenAI Stargate Michigan
Benton, Michigan, United States
IT power not stated
225 km away
OpenAI Stargate Wisconsin
Port Washington, Wisconsin, United States
IT power not stated
Questions
Anthropic-Amazon New Carlisle, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is Anthropic-Amazon New Carlisle?
Anthropic-Amazon New Carlisle is in New Carlisle, Indiana, United States, at 55001 Larrison Blvd, New Carlisle, IN 46552. Epoch AI publishes its coordinates as 41.6794, -86.4712.
Who owns Anthropic-Amazon New Carlisle?
Epoch AI lists Amazon as its owner and Anthropic as its user.
How much power does Anthropic-Amazon New Carlisle use?
Epoch AI estimates its IT power at 1,037 MW as of October 19, 2026, and its total facility power at 1,244 MW. It projects 1,925 MW of IT power by March 17, 2028.
Is Anthropic-Amazon New Carlisle operating?
Yes, and it is growing. Epoch AI counts 18 buildings operating as of October 19, 2026, with more capacity on its timeline.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).