Gigawatt Ledger · Partly energized

Polaris Forge 1, announced against built

Polaris Forge 1 is an SI compute project in Ellendale, North Dakota, by CoreWeave and Applied Digital. The announced figure is 400 MW of critical IT load under lease, from Applied Digital (Jul 1, 2026). Public evidence puts 68 to 175 MW in operation as of June 30, 2026, against 400 MW announced: 17% to 44%. The range covers every figure listed below. Its state today: partly energized.

Announced
400 MW
Energized
68 to 175 MWJun 30, 2026
State
Partly energized
Source links
3

Announced

What was said, and when

Each row is one public announcement about Polaris Forge 1: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

  1. Company statement

    Applied Digital

    Applied Digital Announces 250MW AI Data Center Lease With CoreWeave in North Dakota

    Applied Digital leases 250 MW of critical IT load to CoreWeave at its Ellendale campus, with an option on 150 MW more.

    “deliver 250 megawatts (MW) of critical IT load”
    “designed to host 400 MW of critical IT load”
    “designed to scale up to 1 gigawatt over time”
    “to be ready for service in the fourth quarter of calendar 2025”
    “is expected to be ready for service in the middle of 2026”
    Power or capacity stated
    250 MW of critical IT load, option on 150 MW more; campus designed for 400 MW
    Promised
    First 100 MW building in the fourth quarter of 2025; second building in the middle of 2026; third in 2027
  2. Company statement

    Applied Digital

    Applied Digital Delivers Second Building at Polaris Forge 1

    Applied Digital restates the full lease commitment at the campus.

    “contracted to deliver 400 MW of critical IT load”
    Power or capacity stated
    400 MW of critical IT load under lease
    Promised
    None stated
Not counted

The larger figure, designed to scale up to 1 gigawatt over time (Applied Digital, Jun 2, 2025), is stated as an upper limit or an ambition. It is listed here and left out of the Ledger's total.

Built

What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Partly energized

Public evidence puts 68 to 175 MW in operation as of June 30, 2026, against 400 MW announced: 17% to 44%. The range covers every figure listed below.

  1. Epoch AI estimate

    Epoch AI · Power Map

    CoreWeave Ellendale ND on the Power Map

    Epoch AI counts 1 building operating at CoreWeave Ellendale ND and estimates 68 MW of IT power (88 MW for the whole facility) as of June 30, 2026.

    According to satellite imagery, Building 2 is fully roofed and shell complete, with rooftop chillers mostly installed. Building 3 construction is well underway, with about 1/4 of the roofing done and the foundation laid out.
    IT power running
    68 MW
    Whole facility
    88 MW

    Epoch AI projects 400 MW of IT power by June 1, 2027. A projection, not a fact yet.

  2. Company statement

    Applied Digital

    Applied Digital Delivers Second Building at Polaris Forge 1

    The landlord says the first phase of the second building is ready for service and states the live capacity at the campus.

    “delivering 75 MW of operational AI capacity”
    “bringing total live capacity at the campus to 175 MW”
    Power confirmed
    175 MW
    Used in the total
    Yes

Heat Watch

CoreWeave Ellendale ND: heat seen from space

Over the last three summers NASA's MODIS read the ground here +0.0 °C against the land 5 to 10 km around it by day.

Timeline

Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

  1. Applied Digital: 250 MW of critical IT load, option on 150 MW more; campus designed for 400 MW. Promised: first 100 MW building in the fourth quarter of 2025; second building in the middle of 2026; third in 2027.Announcement · Applied Digital

  2. CoreWeave Ellendale ND: 1 building operating, 50 MW of IT power.Evidence · Epoch AI, on the Power Map

  3. CoreWeave Ellendale ND: 1 building operating, 68 MW of IT power.Evidence · Epoch AI, on the Power Map

  4. CoreWeave Ellendale ND: 1 building operating, 68 MW of IT power.Evidence · Epoch AI, on the Power Map

  5. CoreWeave Ellendale ND: 1 building operating, 68 MW of IT power.Evidence · Epoch AI, on the Power Map

  6. Applied Digital: 400 MW of critical IT load under lease.Announcement · Applied Digital

  7. The landlord says the first phase of the second building is ready for service and states the live capacity at the campus.Evidence · Applied Digital

Corrections

See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

File a correction

Sign in with your SI Passport to file a correction. It is a free message signature and never moves tokens.

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

  • Loading the corrections on file.

Sources

Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.