Gigawatt Ledger · Partly energized

Project Rainier, New Carlisle, announced against built

Project Rainier, New Carlisle is an SI compute project in New Carlisle, Indiana, by Amazon and Anthropic. No source states a power figure for this project alone, so it is not in the Ledger's total. No power figure was announced. Epoch AI estimates 1,037 MW of IT power in operation (1,244 MW for the whole facility) as of October 19, 2026, with more capacity on its timeline. Its state today: partly energized.

Announced
Not stated
Energized
1,037 MW ITOct 19, 2026
State
Partly energized
Source links
3

Announced

What was said, and when

Each row is one public announcement about Project Rainier, New Carlisle: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

  1. Company statement

    Amazon

    AWS's Project Rainier: the world's most powerful computer for training AI

    Amazon describes Project Rainier and its site in St. Joseph County, Indiana, used by Anthropic. It counts chips and states no power figure.

    “nearly half a million Trainium2 chips”
    “Claude is expected to be on more than 1 million Trainium2 chips”
    Power or capacity stated
    None stated
    Promised
    More than 1 million Trainium2 chips by the end of the year
  2. Press report

    The New York Times, reported by The Register

    Amazon Project Rainier: AI supercomputer for Anthropic

    The Register cites a New York Times report for the campus power and an Amazon director for the number of buildings. A press figure is listed, never counted.

    “consume upwards of 2.2 gigawatts of power”
    “will span thirty datacenters at 200,000 square feet apiece”
    Power or capacity stated
    Upwards of 2.2 GW (press report)
    Promised
    None stated

Built

What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Partly energized

No power figure was announced. Epoch AI estimates 1,037 MW of IT power in operation (1,244 MW for the whole facility) as of October 19, 2026, with more capacity on its timeline.

  1. Epoch AI estimate

    Epoch AI · Power Map

    Anthropic-Amazon New Carlisle on the Power Map

    Epoch AI counts 18 buildings operating at Anthropic-Amazon New Carlisle and estimates 1,037 MW of IT power (1,244 MW for the whole facility) as of October 19, 2026.

    Buildings 17-18 are operational. This is an estimate based on a rule of thumb of "operational 5 months after roof is complete", assuming the roofs took one more month after 2025-12-23. Also added four more months to account for commissioning and adjacent cooling units not being complete yet.
    IT power running
    1,037 MW
    Whole facility
    1,244 MW

    Epoch AI projects 1,925 MW of IT power by March 17, 2028. A projection, not a fact yet.

Loading the newest clear pass

Seen from orbit · Compute Watch

The newest clear pass over the site

The image loads from NASA's public imagery: true color at 30 m per pixel, about 5 km across, north up.

Open Compute Watch

Heat Watch

Anthropic-Amazon New Carlisle: heat seen from space

Over the last three summers NASA's MODIS read the ground here +0.7 °C against the land 5 to 10 km around it by day.

Timeline

Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

  1. Amazon: no power figure stated. Promised: more than 1 million Trainium2 chips by the end of the year.Announcement · About Amazon

  2. The New York Times, reported by The Register: Upwards of 2.2 GW (press report).Announcement · The Register

  3. Anthropic-Amazon New Carlisle: 11 buildings operating, 626 MW of IT power.Evidence · Epoch AI, on the Power Map

  4. Anthropic-Amazon New Carlisle: 16 buildings operating, 910 MW of IT power.Evidence · Epoch AI, on the Power Map

  5. Anthropic-Amazon New Carlisle: 16 buildings operating, 910 MW of IT power.Evidence · Epoch AI, on the Power Map

  6. Anthropic-Amazon New Carlisle: 18 buildings operating, 1,037 MW of IT power.Evidence · Epoch AI, on the Power Map

Corrections

See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

File a correction

Sign in with your SI Passport to file a correction. It is a free message signature and never moves tokens.

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.