Power Map · Operating, expanding
Microsoft Fairwater Wisconsin, Mount Pleasant
Microsoft Fairwater Wisconsin is an SI data center in Mount Pleasant, Wisconsin, United States, owned by Microsoft and used by OpenAI (Epoch AI rates this likely), Microsoft (Epoch AI rates this likely). Epoch AI estimates its IT power at 369 MW as of May 15, 2026, with 1 building operating, and projects 2,263 MW by May 13, 2028. Its public timeline starts on July 14, 2023.
- IT power
- 369 MWMay 15, 2026
- Facility power
- 442 MW
- Status
- Operating, expanding
- Buildings operating
- 1
Where it is
The site and its facts
Microsoft Fairwater Wisconsin on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- Mount Pleasant, Wisconsin, United States
- Address
- 4800 90th St, Mount Pleasant, WI 53403
- Coordinates
- 42.6839° N, 87.9152° W
- Owner
- Microsoft
- Users
- OpenAI (Epoch AI rates this likely), Microsoft (Epoch AI rates this likely)
- Project
- Microsoft AI WAN
- Chips
- B200
- Compute
- About 445,680 H100 equivalentsEpoch AI estimate, May 15, 2026
- Energy
- WE Energies
- Projected
- 2,263 MW IT power by May 13, 2028Epoch AI projection, not a fact yet
Seen from orbit · Compute Watch
The newest clear pass over Microsoft Fairwater Wisconsin
The image loads from NASA's public imagery: true color at 30 m per pixel, about 5 km across, north up.
Open Compute WatchThe Gigawatt Ledger · Partly energized
Microsoft Fairwater Wisconsin: announced against built
No power figure was announced for this project. No power figure was announced. Epoch AI estimates 369 MW of IT power in operation (442 MW for the whole facility) as of May 15, 2026, with more capacity on its timeline.
Heat Watch
Microsoft Fairwater Wisconsin: heat seen from space
Over the last three summers NASA's MODIS read the ground here +1.3 °C against the land 5 to 10 km around it by day.
Lights On
Microsoft Fairwater Wisconsin: light at night
NASA's night imagery read 72.3 of 100 over this site in October 2026, against 14.7 in October 2018, the first month read. Against a year before: +15.8 points. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on Microsoft Fairwater Wisconsin, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
Land clearing begins for Building 1.
No IT power yet0 operating
Building 1 cooling and backup generators all look complete from above but there is still construction visible around the building. Building 2 is well underway with a foundation and a complete substation. Large carpark and concrete area north of Building 2. Building 3 has a concrete foundation and a substation underway.
No IT power yet0 operating
Building 1 looks complete, but based on Microsoft announcements, it's not fully operational yet. Steel framing is underway for Building 2.
No IT power yet0 operating
Building 1 is operational. X post from Microsoft saying this date for Fairwater becoming operational.
369 MW1 operating
The main shell of Building 2 looks almost completed. In Area 2 (northwest of Buildings 1-2), the grading for the original design has been replaced with grading for the new 9-building design, making way for Buildings 3-11. Work continues on the northern substation in Area 2.
369 MW1 operating
Building 2 is operational. This is estimated based on (1) the delay between Building 1 and Building 2 starting land clearing, (2) in March 2025, a Microsoft spokesperson said “fully on track” with the first phase , where “southern datacenter buildings complete, and preparation begins for operations” was expected by late 2026. Finally, while it's not 100% consistent with our estimates, MISO was planning 1480 MW of load for Microsoft in Mount Pleasant in 2026.
737 MW2 operating
Buildings 3-11 are estimated to be operational. The grading for this revised 9-building plan was underway in May 2026, and we assume an average 2-year build time from that point.
2,263 MW11 operating
Adopt a site
Watch Microsoft Fairwater Wisconsin
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Microsoft blog with engineering details
- Microsoft blog with more general information
- Construction Permit Application for building 1
- Plan for 9-building and 6-building expansions
- OpenAI article mentioning they use Microsoft's Fairwater supercomputers
- Epoch AI, "AI data centers", the record for Microsoft Fairwater Wisconsin (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
83 km away
OpenAI Stargate Wisconsin
Port Washington, Wisconsin, United States
IT power not stated
163 km away
Anthropic-Amazon New Carlisle
New Carlisle, Indiana, United States
1,037 MW IT power
300 km away
Google Fort Wayne
Fort Wayne, Indiana, United States
IT power not stated
324 km away
Google Cedar Rapids
Cedar Rapids, Iowa, United States
IT power not stated
Questions
Microsoft Fairwater Wisconsin, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is Microsoft Fairwater Wisconsin?
Microsoft Fairwater Wisconsin is in Mount Pleasant, Wisconsin, United States, at 4800 90th St, Mount Pleasant, WI 53403. Epoch AI publishes its coordinates as 42.6839, -87.9152.
Who owns Microsoft Fairwater Wisconsin?
Epoch AI lists Microsoft as its owner and OpenAI (Epoch AI rates this likely), Microsoft (Epoch AI rates this likely) as its users.
How much power does Microsoft Fairwater Wisconsin use?
Epoch AI estimates its IT power at 369 MW as of May 15, 2026, and its total facility power at 442 MW. It projects 2,263 MW of IT power by May 13, 2028.
Is Microsoft Fairwater Wisconsin operating?
Yes, and it is growing. Epoch AI counts 1 building operating as of May 15, 2026, with more capacity on its timeline.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).