Power Map · Operating, expanding
Meta Prometheus, New Albany
Meta Prometheus is an SI data center in New Albany, Ohio, United States, owned by Meta and used by Meta. Epoch AI estimates its IT power at 471 MW as of August 31, 2026, with 10 buildings operating, and projects 1,022 MW by July 1, 2028. Its public timeline starts on April 14, 2022.
- IT power
- 471 MWAug 31, 2026
- Facility power
- 612 MW
- Status
- Operating, expanding
- Buildings operating
- 10
Where it is
The site and its facts
Meta Prometheus on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- New Albany, Ohio, United States
- Address
- 1 Community Cir, New Albany, OH 43054
- Coordinates
- 40.0878° N, 82.7428° W
- Owner
- Meta
- Users
- Meta
- Project
- Prometheus
- Chips
- B300
- Compute
- About 536,343 H100 equivalentsEpoch AI estimate, Aug 31, 2026
- Energy
- Williams, American Electric Power
- Projected
- 1,022 MW IT power by July 1, 2028Epoch AI projection, not a fact yet
Seen from orbit · Compute Watch
The newest clear pass over Meta Prometheus
The image loads from NASA's public imagery: true color at 30 m per pixel, about 5 km across, north up.
Open Compute WatchThe Gigawatt Ledger · Partly energized
Meta Prometheus: announced against built
1 GW was announced for this project. Public evidence puts 471 to 612 MW in operation as of August 31, 2026, against 1 GW announced: 47% to 61%. The low end is the IT load, the high end the whole facility, because the announcement does not say which it means.
Heat Watch
Meta Prometheus: heat seen from space
Over the last three summers NASA's MODIS read the ground here +2.3 °C against the land 5 to 10 km around it by day.
Lights On
Meta Prometheus: light at night
NASA's night imagery read 80.6 of 100 over this site in October 2026, against 37.7 in October 2018, the first month read. Against a year before: +1.1 points. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on Meta Prometheus, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
Land clearing begins for Building 1-2
No IT power yet0 operating
Roof complete on Building 5 (QTS-owned). In the northernmost area, land clearing begins on a new Meta site for Buildings 16-20. Building 1 still has construction work around the building and cooling equipment, so it's unlikely to be operational.
No IT power yet0 operating
Building 4 operational. Based on our default estimate of roof-to-operational time.
No IT power yet0 operating
Building 1 is operational, based on there being minimal construction work and cars in the main carpark. Building 2 still has some construction work around the building. Building 18 roof is complete. The on-site power at Socrates South and Socrates North has some outlines of gas turbines, to be installed later.
76 MW1 operating
Buildings 2-6 are operational, based on all equipment being in place, the paved ground, and minimal construction equipment by the buildings. Buildings 7-11 all have some kind of power or cooling equipment lining their right side which are not fully installed. Building 14 has chillers installed. Buildings 16-20 roofs are complete. The Socrates South power plant to the right of Buildings 7-11 has 7 gas turbines in place, judging by the exhaust stacks.
368 MW6 operating
The Socrates South power plant to the right of Buildings 7-12 now has 10 natural gas turbines in place, judging by the number of exhaust stacks. Battery backup has been installed nearby. To the north, a new section of tent buildings has begun east of Buildings 16-20.
368 MW6 operating
Building 7-11 (Meta tents) look structurally complete but not operational, given there is still construction activity, including at the adjacent Socrates South power plant. Northern tents (Buildings 16-27) are all roofed except for 21 and 27.
368 MW6 operating
Buildings 7-10 (tents) are operational, based on infrared drone video from RAAD (raad.com) captured on this date. The video suggests that 138.8 MW of nameplate turbine capacity is operating at the Socrates South power plant (about 69% of the 200 MW nameplate capacity), and Buildings 7-10 roof vents are bright on infrared while Buildings 11-12 vents are not. That's 4/6 buildings operating, implying about 67% of capacity, which is consistent with 69% of the power plant operating. In the north, Buildings 16-27 (tents) look to be in a completed state. Each northern set of 6 tents still awaits to be connected to one of the corresponding power plants to become operational. Drone video from August 19th shows no turbines operating at Socrates North, though there are 3 small diesel generators operating. Building 13 (Vantage) is still under construction, we estimate another 3 months before operability.
471 MW10 operating
Socrates South and Socrates North gas power plants are fully operational, enabling the operability of Buildings 11-12 and 16-21. This completes the 2 sets of 6 tents associated with Socrates South and Socrates North. This is based on documents stating "late Third or early Fourth Quarter of 2026", "late 2026", "November 2026", "third quarter of 2026". The timeline also lines up with RAAD drone imagery from 09/08/26 seeing operating turbines at Socrates South and a full set of turbines installed but not yet operating at Socrates North.
676 MW18 operating
Building 13 (Vantage) is operational, based on the pace of construction seen in earlier images.
740 MW19 operating
Building 14 (Vantage) is operational, based on it starting construction about 3 months after Building 13.
804 MW20 operating
Building 15 (Vantage) operational, based on it starting construction about 3 months after Building 14.
868 MW21 operating
Buildings 22-27 (3rd set of 6 Meta tents) are operational. This is a conservative estimate to align with the operability of the Socrates the Younger power plant. The power plant is operational by Q3 of 2028 based on the project schedule. It is announced to produce a maximum of 250MW.
1,022 MW27 operating
Adopt a site
Watch Meta Prometheus
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Meta blog post with details on Prometheus
- New Albany Business Park land use map
- Letter on Socrates South Power Generation Project
- Epoch AI, "AI data centers", the record for Meta Prometheus (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
Questions
Meta Prometheus, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is Meta Prometheus?
Meta Prometheus is in New Albany, Ohio, United States, at 1 Community Cir, New Albany, OH 43054. Epoch AI publishes its coordinates as 40.0878, -82.7428.
Who owns Meta Prometheus?
Epoch AI lists Meta as its owner and Meta as its user.
How much power does Meta Prometheus use?
Epoch AI estimates its IT power at 471 MW as of August 31, 2026, and its total facility power at 612 MW. It projects 1,022 MW of IT power by July 1, 2028.
Is Meta Prometheus operating?
Yes, and it is growing. Epoch AI counts 10 buildings operating as of August 31, 2026, with more capacity on its timeline.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).