Gigawatt Ledger · Partly energized

Microsoft Fairwater Wisconsin, announced against built

Microsoft Fairwater Wisconsin is an SI compute project in Mount Pleasant, Wisconsin, by Microsoft. No source states a power figure for this project alone, so it is not in the Ledger's total. No power figure was announced. Epoch AI estimates 369 MW of IT power in operation (442 MW for the whole facility) as of May 15, 2026, with more capacity on its timeline. Its state today: partly energized.

Announced
Not stated
Energized
369 MW ITMay 15, 2026
State
Partly energized
Source links
2

Announced

What was said, and when

Each row is one public announcement about Microsoft Fairwater Wisconsin: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

  1. Company statement

    Microsoft

    Made in Wisconsin: The world's most powerful AI datacenter

    Microsoft announces the Fairwater datacenter in Mount Pleasant and a second one. It states money and a date, and no power figure.

    “bring this AI datacenter online in early 2026”
    “an additional $4 billion to be spent in the next three years”
    Power or capacity stated
    None stated
    Promised
    Online in early 2026; a second datacenter within three years

Built

What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Partly energized

No power figure was announced. Epoch AI estimates 369 MW of IT power in operation (442 MW for the whole facility) as of May 15, 2026, with more capacity on its timeline.

  1. Epoch AI estimate

    Epoch AI · Power Map

    Microsoft Fairwater Wisconsin on the Power Map

    Epoch AI counts 1 building operating at Microsoft Fairwater Wisconsin and estimates 369 MW of IT power (442 MW for the whole facility) as of May 15, 2026.

    The main shell of Building 2 looks almost completed. In Area 2 (northwest of Buildings 1-2), the grading for the original design has been replaced with grading for the new 9-building design, making way for Buildings 3-11. Work continues on the northern substation in Area 2.
    IT power running
    369 MW
    Whole facility
    442 MW

    Epoch AI projects 2,263 MW of IT power by May 13, 2028. A projection, not a fact yet.

Loading the newest clear pass

Seen from orbit · Compute Watch

The newest clear pass over the site

The image loads from NASA's public imagery: true color at 30 m per pixel, about 5 km across, north up.

Open Compute Watch

Heat Watch

Microsoft Fairwater Wisconsin: heat seen from space

Over the last three summers NASA's MODIS read the ground here +1.3 °C against the land 5 to 10 km around it by day.

Timeline

Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

  1. Microsoft: no power figure stated. Promised: online in early 2026; a second datacenter within three years.Announcement · Microsoft On the Issues

  2. Microsoft Fairwater Wisconsin: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map

  3. Microsoft Fairwater Wisconsin: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map

  4. Microsoft Fairwater Wisconsin: 1 building operating, 369 MW of IT power.Evidence · Epoch AI, on the Power Map

  5. Microsoft Fairwater Wisconsin: 1 building operating, 369 MW of IT power.Evidence · Epoch AI, on the Power Map

Corrections

See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

File a correction

Sign in with your SI Passport to file a correction. It is a free message signature and never moves tokens.

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

  • Loading the corrections on file.