Power Map · Operating
QTS Richmond 1, Sandston
QTS Richmond 1 is an SI data center in Sandston, Virginia, United States. Epoch AI estimates its IT power at 238 MW as of February 13, 2026, with 5 buildings operating. Its public timeline starts on October 1, 2023.
- IT power
- 238 MWFeb 13, 2026
- Facility power
- 333 MW
- Status
- Operating
- Buildings operating
- 5
Where it is
The site and its facts
QTS Richmond 1 on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- Sandston, Virginia, United States
- Address
- 6000 Technology Blvd, Sandston, VA 23150
- Coordinates
- 37.4855° N, 77.2469° W
- Owner
- Not public
- Compute
- About 242,547 H100 equivalentsEpoch AI estimate, Feb 13, 2026
- Energy
- Dominion Energy
Heat Watch
QTS Richmond 1: heat seen from space
Over the last three summers NASA's MODIS read the ground here +0.0 °C against the land 5 to 10 km around it by day, a change of +0.5 °C since before work on this build began.
Lights On
QTS Richmond 1: light at night
NASA's night imagery read 63.6 of 100 over this site in October 2026, against 25.9 in October 2018, the first month read. Against a year before: +8.5 points. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on QTS Richmond 1, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
Land cleared for site expansion, some materials down at substation site. We assume that Buildings 1 and 2 are not running AI workloads at this point due to the lack of cooling infrastructure.
No IT power yet0 operating
Building 1 and 2 retrofitting has begun (see Google Earth). Building 1 has chillers added to the roof and perimeter, and backup generators added to the perimeter.
No IT power yet0 operating
Building 1 (retrofitted) is operational. This is based on it looking complete, and cooling towers possibly showing water vapor plumes, in this Google Earth image. Building 2 has chillers added to the roof and perimeter, and backup generators added to the perimeter. Cooling towers near Building 2 have been removed. Building 3 shell is under construction.
47 MW1 operating
Building 2 (retrofitted) is operational. This is based on Building 2 looking compelte, and construction around Building 1 and 2 being mostly cleared. A colored motion artifact on one of the Building 1 cooling tower fans suggests it is moving. Building 3 cooling is installed, backup generators partly installed. Building 4 shell is under construction.
94 MW2 operating
Building 3 is operational, based on the building looking complete and the carpark to the south being full. Three more backup generators added to the Building 1 and 2 area, with a lot more construction equipment again (but this could be a laydown area for Richmond 2). Building 4 has cooling and backup generators fully installed. Building 5 has cooling installed, and backup generators partly installed.
142 MW3 operating
Building 4 is operational, based on a complete building and full carpark in a Google Earth image. Building 5 does not seem quite operational given the empty carpark and construction activity at the perimeter.
190 MW4 operating
Building 5 is operational, based on a complete building and full carpark in a Google Earth image. Construction equipment around Building 1 and 2 has cleared up again.
238 MW5 operating
No changes to the site since November 2025.
238 MW5 operating
No changes to the site since December 2025.
238 MW5 operating
Adopt a site
Watch QTS Richmond 1
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Richmond 1 factsheet
- Environmental permit detailing power generation
- Epoch AI, "AI data centers", the record for QTS Richmond 1 (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
0 km away
QTS Richmond 2
Sandston, Virginia, United States
180 MW IT power
1 km away
QTS Richmond 3
Sandston, Virginia, United States
144 MW IT power
16 km away
CoreWeave Chester VA
Chester, Virginia, United States
82 MW IT power
142 km away
STACK Infrastructure NVA02
Manassas, Virginia, United States
85 MW IT power
Questions
QTS Richmond 1, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is QTS Richmond 1?
QTS Richmond 1 is in Sandston, Virginia, United States, at 6000 Technology Blvd, Sandston, VA 23150. Epoch AI publishes its coordinates as 37.4855, -77.2469.
Who owns QTS Richmond 1?
Epoch AI does not name an owner yet.
How much power does QTS Richmond 1 use?
Epoch AI estimates its IT power at 238 MW as of February 13, 2026, and its total facility power at 333 MW.
Is QTS Richmond 1 operating?
Yes. Epoch AI counts 5 buildings operating as of February 13, 2026.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).