Gigawatt Ledger · Under construction
Meta Hyperion, announced against built
Meta Hyperion is an SI compute project in Richland Parish, Louisiana, by Meta. The announced figure is over two gigawatts of compute capacity, from Meta (Nov 11, 2026 (undated page, read on this date)). Epoch AI tracks the site as under construction, with no building operating as of April 19, 2026. Its state today: under construction.
- Announced
- 2 GW
- Energized
- NoneApr 19, 2026
- State
- Under construction
- Source links
- 4
Announced
What was said, and when
Each row is one public announcement about Meta Hyperion: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.
- Company statement, quoted by the press
Mark Zuckerberg and Meta, reported by TechCrunch
Mark Zuckerberg says Meta is building a 5GW AI data center
TechCrunch reports Mark Zuckerberg's Threads post and a Meta spokesperson's dates for Hyperion.
“bring two gigawatts of data center capacity online by 2030”
“would scale to five gigawatts in several years”
- Power or capacity stated
- 2 GW, scaling to 5 GW
- Promised
- 2 GW online by 2030
- Company statement
Meta
Meta's Infrastructure Evolution and the Advent of AI
Meta's engineering blog describes Hyperion and when it starts to come online.
“will have the ability to scale up to a capacity of 5 gigawatts”
“expected to come online beginning in 2028”
- Power or capacity stated
- Ability to scale up to 5 GW
- Promised
- Online beginning in 2028
- Undated page, read on this dateCompany statement
Meta
The largest Meta data center yet brings big impact to Louisiana
Meta's page for the Richland Parish data center, first announced in December 2024.
“The data center will deliver over two gigawatts of compute capacity to train future open-source large language models.”
“delivering 5 gigawatts of compute capacity to house Hyperion, our largest multi-gigawatt AI cluster”
- Power or capacity stated
- Over 2 GW of compute capacity; 5 GW for Hyperion
- Promised
- None stated
The larger figure, scale up to 5 gigawatts (Meta, Sep 29, 2025), is stated as an upper limit or an ambition. It is listed here and left out of the Ledger's total.
Built
What public evidence confirms
What is on the ground today, from the Power Map data and from any statement or filing that states live power.
Epoch AI tracks the site as under construction, with no building operating as of April 19, 2026.
- Epoch AI estimate
Epoch AI · Power Map
Meta Hyperion on the Power Map
Epoch AI tracks Meta Hyperion as under construction: no building is operating as of April 19, 2026.
Building 1 and 2 roof is finished and cooling is at an advanced stage of installation. Building 3 and 6 roof and cooling in progress.
- IT power running
- None
- Whole facility
- None
Epoch AI projects 1,632 MW of IT power by January 1, 2028. A projection, not a fact yet.
Seen from orbit · Compute Watch
The newest clear pass over the site
The image loads from NASA's public imagery: true color at 30 m per pixel, about 5 km across, north up.
Open Compute WatchHeat Watch
Meta Hyperion: heat seen from space
Over the last three summers NASA's MODIS read the ground here +1.6 °C against the land 5 to 10 km around it by day.
Timeline
Announcements and evidence, by date
What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.
Meta Hyperion: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map
Mark Zuckerberg and Meta, reported by TechCrunch: 2 GW, scaling to 5 GW. Promised: 2 GW online by 2030.Announcement · TechCrunch
Meta: Ability to scale up to 5 GW. Promised: online beginning in 2028.Announcement · Engineering at Meta
Meta Hyperion: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map
Meta Hyperion: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map
Meta: Over 2 GW of compute capacity; 5 GW for Hyperion.Announcement · Meta Data Centers, undated page read on this date
Corrections
See something wrong? File a correction
Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.
File a correction
Sign in with your SI Passport to file a correction. It is a free message signature and never moves tokens.
A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.
Corrections on file · 0
- Loading the corrections on file.
Sources
Every link behind this page
Read on November 11, 2026. An undated page carries the date it was read.
- Mark Zuckerberg says Meta is building a 5GW AI data center, TechCrunch, Jul 14, 2025
- Meta's Infrastructure Evolution and the Advent of AI, Engineering at Meta, Sep 29, 2025
- The largest Meta data center yet brings big impact to Louisiana, Meta Data Centers, Nov 11, 2026 (undated page, read on this date)
- Meta Hyperion on the Power Map, from Epoch AI, "AI data centers" (CC BY 4.0), retrieved November 10, 2026
More projects
Keep reading the Ledger
Three more projects, the same operator first.
The whole Ledger- Partly energized
Meta Prometheus
New Albany, Ohio
1 GW announced · 471 to 612 MW
Open the project - Partly energized
Colossus (Memphis and Southaven)
Memphis, Tennessee
2 GW announced · 1 to 1.7 GW
Open the project - Under construction
Stargate Shackelford County (Frontier)
Shackelford County, Texas
1.4 GW announced · nothing confirmed
Open the project