Microsoft Fairwater Atlanta, announced against built
Microsoft Fairwater Atlanta is an SI compute project in Fayetteville, Georgia, by Microsoft. No source states a power figure for this project alone, so it is not in the Ledger's total. No power figure was announced. Epoch AI estimates 636 MW of IT power in operation (859 MW for the whole facility) as of June 14, 2026. Its state today: energized.
- Announced
- Not stated
- Energized
- 636 MW ITJun 14, 2026
- State
- Energized
- Source links
- 2
Announced
What was said, and when
Each row is one public announcement about Microsoft Fairwater Atlanta: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.
- Company statement
Microsoft
Infinite scale: The architecture behind the Azure AI superfactory
Microsoft unveils its Fairwater site in Atlanta, Georgia. It states no power figure for the site.
“Today, we are unveiling the next Fairwater site of Azure AI datacenters in Atlanta, Georgia.”
- Power or capacity stated
- None stated
- Promised
- None stated
Built
What public evidence confirms
What is on the ground today, from the Power Map data and from any statement or filing that states live power.
No power figure was announced. Epoch AI estimates 636 MW of IT power in operation (859 MW for the whole facility) as of June 14, 2026.
- Epoch AI estimate
Epoch AI · Power Map
Microsoft Fairwater Atlanta on the Power Map
Epoch AI counts 4 buildings operating at Microsoft Fairwater Atlanta and estimates 636 MW of IT power (859 MW for the whole facility) as of June 14, 2026.
Building 3 and 4 are operational.
- IT power running
- 636 MW
- Whole facility
- 859 MW
Heat Watch
Microsoft Fairwater Atlanta: heat seen from space
Over the last three summers NASA's MODIS read the ground here -0.2 °C against the land 5 to 10 km around it by day.
Timeline
Announcements and evidence, by date
What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.
Microsoft Fairwater Atlanta: 2 buildings operating, 321 MW of IT power.Evidence · Epoch AI, on the Power Map
Microsoft: no power figure stated.Announcement · The Official Microsoft Blog
Microsoft Fairwater Atlanta: 2 buildings operating, 321 MW of IT power.Evidence · Epoch AI, on the Power Map
Microsoft Fairwater Atlanta: 2 buildings operating, 321 MW of IT power.Evidence · Epoch AI, on the Power Map
Microsoft Fairwater Atlanta: 4 buildings operating, 636 MW of IT power.Evidence · Epoch AI, on the Power Map
Corrections
See something wrong? File a correction
Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.
File a correction
Sign in with your SI Passport to file a correction. It is a free message signature and never moves tokens.
A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.
Corrections on file · 0
- Loading the corrections on file.
Sources
Every link behind this page
Read on November 11, 2026. An undated page carries the date it was read.
- Infinite scale: The architecture behind the Azure AI superfactory, The Official Microsoft Blog, Nov 12, 2025
- Microsoft Fairwater Atlanta on the Power Map, from Epoch AI, "AI data centers" (CC BY 4.0), retrieved November 10, 2026
More projects
Keep reading the Ledger
Three more projects, the same operator first.
The whole Ledger- Under construction
Abilene campus for Microsoft
Abilene, Texas
900 MW announced · nothing confirmed
Open the project - Partly energized
Microsoft Fairwater Wisconsin
Mount Pleasant, Wisconsin
No power figure stated · 369 MW IT
Open the project - Partly energized
Colossus (Memphis and Southaven)
Memphis, Tennessee
2 GW announced · 1 to 1.7 GW