1. Home
  2. Gigawatt Ledger
  3. Abilene campus for Microsoft

Gigawatt Ledger · Under construction

Abilene campus for Microsoft, announced against built

Abilene campus for Microsoft is an SI compute project in Abilene, Texas, by Microsoft and Crusoe. The announced figure is 900 MW site, from Crusoe (Mar 27, 2026). Epoch AI tracks the site as under construction, with no building operating as of January 15, 2026. Its state today: under construction.

Announced
900 MW
Energized
NoneJan 15, 2026
State
Under construction
Source links
2

Announced

What was said, and when

Each row is one public announcement about Abilene campus for Microsoft: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

  1. Company statement

    Crusoe

    Crusoe builds 900 MW Abilene campus for Microsoft

    Crusoe announces a new 900 MW campus in Abilene for Microsoft: two buildings and an on-site power plant.

    “the 900 MW site includes two new buildings and an onsite power plant to support grid resilience”
    “Each of the two new buildings is designed to deliver 336 MW of critical IT load”
    “the first building expected to be energized in mid-2027”
    “bringing the total projected capacity across the full Abilene site to 2.1 gigawatts (GW)”
    Power or capacity stated
    900 MW site; 336 MW of critical IT load in each of two buildings
    Promised
    First building energized in mid-2027

Built

What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Under construction

Epoch AI tracks the site as under construction, with no building operating as of January 15, 2026.

  1. Epoch AI estimate

    Epoch AI · Power Map

    Crusoe Abilene Expansion on the Power Map

    Epoch AI tracks Crusoe Abilene Expansion as under construction: no building is operating as of January 15, 2026.

    Land clearing continues.
    IT power running
    None
    Whole facility
    None

    Epoch AI projects 672 MW of IT power by November 11, 2027. A projection, not a fact yet.

Heat Watch

Crusoe Abilene Expansion: heat seen from space

Over the last three summers NASA's MODIS read the ground here -0.4 °C against the land 5 to 10 km around it by day.

Timeline

Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

  1. Crusoe Abilene Expansion: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map

  2. Crusoe Abilene Expansion: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map

  3. Crusoe: 900 MW site; 336 MW of critical IT load in each of two buildings. Promised: first building energized in mid-2027.Announcement · Crusoe

Corrections

See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

File a correction

Sign in with your SI Passport to file a correction. It is a free message signature and never moves tokens.

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

  • Loading the corrections on file.

Sources

Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.