Power Map · Operating

OpenAI Stargate Abilene, Abilene

OpenAI Stargate Abilene is an SI data center in Abilene, Texas, United States, owned by Oracle and used by OpenAI. Epoch AI estimates its IT power at 824 MW as of November 1, 2026, with 8 buildings operating. Its public timeline starts on May 31, 2024.

IT power
824 MWNov 1, 2026
Facility power
1,154 MW
Status
Operating
Buildings operating
8

Where it is

The site and its facts

OpenAI Stargate Abilene on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Abilene, Texas, United StatesOpen in OpenStreetMap
Place
Abilene, Texas, United States
Address
5502 Spinks Rd, Abilene, TX 79601
Coordinates
32.5013° N, 99.7856° W
Owner
Oracle
Users
OpenAI
Project
Stargate
Chips
B200, B300
Compute
About 1,018,696 H100 equivalentsEpoch AI estimate, Nov 1, 2026
Energy
American Electric Power
Builders
Mortenson
Loading the newest clear pass

Seen from orbit · Compute Watch

The newest clear pass over OpenAI Stargate Abilene

The image loads from NASA's public imagery: true color at 30 m per pixel, about 5 km across, north up.

Open Compute Watch

The Gigawatt Ledger · Energized

Stargate Abilene: announced against built

1.2 GW was announced for this project. Public evidence puts 1.15 GW in operation as of November 1, 2026, against 1.2 GW announced: 96%. The announcement states total power, so it is set against the power of the whole facility.

Heat Watch

OpenAI Stargate Abilene: heat seen from space

Over the last three summers NASA's MODIS read the ground here -0.7 °C against the land 5 to 10 km around it by day.

Lights On

OpenAI Stargate Abilene: light at night

NASA's night imagery read 58.4 of 100 over this site in October 2026, against 2.4 in October 2018, the first month read. Against a year before: +2.6 points. Light is not proof of what runs inside.

Timeline

Dated, from the public record

Epoch AI's dated notes on OpenAI Stargate Abilene, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

  1. Land clearing begins for northern two buildings (Building 1-2)

    No IT power yet0 operating

  2. Building 1 looks close to finishing construction, with chillers in place. OpenAI stated that "Oracle began delivering the first NVIDIA GB200 racks in June." The "tenant improvement" work is not due until September, however.

    No IT power yet0 operating

  3. Building 1 is fully operational around this date. The first phase was "live" on September 30 according a Crusoe announcement. While the first phase consists of Building 1 and 2, the language doesn't outright confirm that both buildings are fully operational. The announcement also stated that "Oracle began delivering the first NVIDIA GB200 racks in June", and we think 3 months is enough time to ram to 50,000 GB200s in Building 1. The satellite image also suggests that Building 1 is complete (shell and equipment done, many cars neatly parked) while Building 2 is ongoing (trucks and construction equipment still present). The 200 MW substation built in 2022 and expanded in 2024 is enough to power both buildings. To the right of Building 2, five gas turbines are in place with five more turbines still under construction. Chillers are partly installed for Building 3. Roof is complete for Building 4. The larger 1 GW substation is not complete yet.

    103 MW1 operating

  4. Building 2 is fully operational. This exact date corresponds to the expected completion date of "Four (4) data hall spaces and an administrative office build-out" according to a TDLR filing, but this date is also consistent with satellite imagery. By January 15, Building 2 looked as finished as Building 1, whereas on September 26 it did not look finished.

    206 MW2 operating

  5. The 1 GW substation looks close to completion. Building 3 appears to have all power and cooling equipment installed, but there are still signs of construction work. This seems on track for operation in 3 months. Building 4 has about 80% of chillers installed. Other buildings have few or no chillers installed.

    206 MW2 operating

  6. Building 3 and 4 look complete, but are not fully operational. Not as many cars are parked next to it as Building 1-2 which suggests they may still be ramping up. Building 4 was due by now according to a regulatory filing. Building 5 still has light construction activity, while Building 6 still lacks chillers. The on-site power plant to the right of Building 2 looks complete.

    206 MW2 operating

  7. Buildings 3 and 4 are estimated to be operational. On April 22nd, Oracle posted that "In Abilene, 200MW is already operational". This suggests that there was still only Building 1 and 2 operational. Since Buildings 3 and 4 looked complete from the outside on March 24th, we give it another month after Oracle's post for them to be operational. This would also give the buildings a similar 1 year 4 months timeline that Buildings 1 took from land clearing to being operational.

    412 MW4 operating

  8. Buildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing). The substation looks complete.

    412 MW4 operating

  9. Buildings 5-6 are operational. On Oracle's Q1 FY27 earnings call (September 10, 2026), Clay Magouyrk said "6 of the 8 campus buildings, representing 618 megawatts and 75% of total capacity have now been delivered to the customer" (transcript). 618 MW = 6 x 103 MW, matching the per-building IT power figure Crusoe reported earlier. Since Oracle is the chip owner rather than the facility operator, we assume "delivered" means the chips are installed and ready to use.

    618 MW6 operating

  10. Buildings 7-8 are estimated to be operational. On March 24, Building 8 roughly looked like where Building 3 was in September. Building 3 is estimated to be operational in April, 7 months later. This naively suggests Building 8 will be operational by early November, 7 months after March 24. Oracle gave no date for the last two buildings on its September 10 call.

    824 MW8 operating

Adopt a site

Watch OpenAI Stargate Abilene

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

The watcher

Loading the watcher.

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

  • Approved updates show here with their date.

Sources

Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

Questions

OpenAI Stargate Abilene, answered

Where it is, who owns it and how much power it uses, from the public record.

Where is OpenAI Stargate Abilene?

OpenAI Stargate Abilene is in Abilene, Texas, United States, at 5502 Spinks Rd, Abilene, TX 79601. Epoch AI publishes its coordinates as 32.5013, -99.7856.

Who owns OpenAI Stargate Abilene?

Epoch AI lists Oracle as its owner and OpenAI as its user.

How much power does OpenAI Stargate Abilene use?

Epoch AI estimates its IT power at 824 MW as of November 1, 2026, and its total facility power at 1,154 MW.

Is OpenAI Stargate Abilene operating?

Yes. Epoch AI counts 8 buildings operating as of November 1, 2026.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).