Power Map · Under construction

OpenAI Stargate Shackelford, Abilene

OpenAI Stargate Shackelford is an SI data center in Abilene, Texas, United States, owned by Oracle and used by OpenAI. Epoch AI tracks it as under construction: no building is operating yet as of September 4, 2026, and projects 1,400 MW by November 11, 2028. Its public timeline starts on August 1, 2025.

IT power
Not statedEpoch AI
Facility power
Not stated
Status
Under construction
Buildings operating
0

Where it is

The site and its facts

OpenAI Stargate Shackelford on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Abilene, Texas, United StatesOpen in OpenStreetMap
Place
Abilene, Texas, United States
Address
175 Private Road 1604, Abilene, TX 79601, Shackelford County
Coordinates
32.5438° N, 99.5483° W
Owner
Oracle
Users
OpenAI
Project
Stargate
Projected
1,400 MW IT power by November 11, 2028Epoch AI projection, not a fact yet

The Gigawatt Ledger · Under construction

Stargate Shackelford County: announced against built

1.4 GW was announced for this project. Epoch AI tracks the site as under construction, with no building operating as of September 4, 2026.

Heat Watch

OpenAI Stargate Shackelford: heat seen from space

Over the last three summers NASA's MODIS read the ground here +0.7 °C against the land 5 to 10 km around it by day.

Lights On

OpenAI Stargate Shackelford: light at night

NASA's night imagery read 62.4 of 100 over this site in October 2026, against 0.8 in October 2018, the first month read. Against a year before: +60.0 points. Light is not proof of what runs inside.

Timeline

Dated, from the public record

Epoch AI's dated notes on OpenAI Stargate Shackelford, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

  1. Land clearing begins.

    No IT power yet0 operating

  2. The layout of Buildings 1-5 is visible. Steel framing has just started on Building 1.

    No IT power yet0 operating

  3. Steel framing is underway for Buildings 1-3, and roofing is underway for Building 1.

    No IT power yet0 operating

  4. Buildings 1-5 shells complete and fully roofed. Buildings 1-3 appear to be actively installing cooling and backup generators nearby. The pads for Buildings 6-10 to the north have also been visibly cleared, with foundations for Buildings 6 and 7 underway.

    No IT power yet0 operating

  5. Building 1 is operational (estimate). TDLR lists the construction completion date for Building 1 as 2027-02-15. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    140 MW1 operating

  6. Building 2 is operational (estimate). TDLR lists the construction completion date for Building 2 as 2027-04-19. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    280 MW2 operating

  7. Building 3 is operational (estimate). TDLR lists the construction completion date for Building 3 as 2027-05-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    420 MW3 operating

  8. Building 4 is operational (estimate). TDLR lists the construction completion date for Building 4 as 2027-08-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    560 MW4 operating

  9. Building 5 is operational (estimate). TDLR lists the construction completion date for Building 5 as 2027-09-08. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    700 MW5 operating

  10. Building 6 is operational (estimate). TDLR lists the construction completion date for Building 6 as 2027-10-04. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    840 MW6 operating

  11. Building 7 is operational (estimate). TDLR lists the construction completion date for Building 7 as 2027-11-12. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    980 MW7 operating

  12. Building 8 is operational (estimate). TDLR lists the construction completion date for Building 8 as 2028-04-17. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    1,120 MW8 operating

  13. Building 9 is operational (estimate). TDLR lists the construction completion date for Building 9 as 2028-04-18. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    1,260 MW9 operating

  14. Building 10 is operational (estimate). TDLR lists the construction completion date for Building 10 as 2028-05-11. We add 6 months for commissioning, installation etc. before assuming the building is fully operational.

    1,400 MW10 operating

Adopt a site

Watch OpenAI Stargate Shackelford

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

The watcher

Loading the watcher.

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

  • Approved updates show here with their date.

Sources

Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

Questions

OpenAI Stargate Shackelford, answered

Where it is, who owns it and how much power it uses, from the public record.

Where is OpenAI Stargate Shackelford?

OpenAI Stargate Shackelford is in Abilene, Texas, United States, at 175 Private Road 1604, Abilene, TX 79601, Shackelford County. Epoch AI publishes its coordinates as 32.5438, -99.5483.

Who owns OpenAI Stargate Shackelford?

Epoch AI lists Oracle as its owner and OpenAI as its user.

How much power does OpenAI Stargate Shackelford use?

No building is operating yet, so Epoch AI states no IT power for it today. It projects 1,400 MW of IT power by November 11, 2028.

Is OpenAI Stargate Shackelford operating?

Not yet. Epoch AI tracks it as under construction, with no building operating on its latest entry.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).