- Home
- Onsite Power Watch
- Richland Parish 1 to 4 and Pointe Coupee 1 to 3
Onsite Power Watch · Gas
Richland Parish 1 to 4 and Pointe Coupee 1 to 3
Richland Parish 1 to 4 and Pointe Coupee 1 to 3: seven combined cycle gas units and three battery systems, 5,278 MW of gas units. It serves a second Meta data center in north Louisiana, to be developed by Evest LLC. Status: proposed, as of November 2, 2026. Entergy Louisiana application to the LPSC of March 2026; a settlement recommends certification; LPSC decision expected in December 2026.
- Size
- 5,278 MW
- Fuel
- Gas
- Status
- Proposed
- As of
- Nov 2, 2026
The facts
What the public record shows
Utility plants on the grid, certified to serve one customer. Each fact below names its source.
- In March 2026 Entergy Louisiana signed a service agreement with Evest LLC, a Meta subsidiary, and applied to build seven combined cycle units totaling 5,278 MW, four near the customer site in Richland Parish and three in Pointe Coupee Parish (Entergy, Form 10-Q, November 2, 2026).
- A settlement with the LPSC staff and one intervenor recommends certification. Entergy expects the decision in December 2026 and in service dates in 2030 and 2031.
The filing
The permit or filing behind it
The regulator's decision or the owner's filing that the status rests on.
Proposed · Nov 2, 2026
Entergy Louisiana application to the LPSC of March 2026; a settlement recommends certification; LPSC decision expected in December 2026.
The site
The data center it serves
Linked to the Power Map only where a source ties the two.
Not on the Power Map
A second Meta data center in north Louisiana, to be developed by Evest LLC. No source read ties this plant to a site the Power Map lists, so no site is linked.
Sources
Where every fact comes from
Each source was opened and read on November 23, 2026.
Nov 2, 2026, read Nov 23, 2026
Entergy
Quarterly report for the quarter ended September 30, 2026 (SEC Form 10-Q)
Keep going
The grid around it
The same place, other records.
The Queue: MISO
How much power data centers are asking MISO for.
See the queueOnsite Power Watch
Every plant built to run a data center directly.
Every plantGrid Watch
Live demand on the grids that host the most sites.
Watch the gridsGigawatt Ledger
What was announced against what is confirmed energized.
Read the LedgerQuestions
Richland Parish 1 to 4 and Pointe Coupee 1 to 3, answered
The plant, its status and the sources.
What is Richland Parish 1 to 4 and Pointe Coupee 1 to 3?
Seven combined cycle gas units and three battery systems, 5,278 MW of gas units, built to serve A second Meta data center in north Louisiana, to be developed by Evest LLC. Utility plants on the grid, certified to serve one customer.
What is its status?
Proposed, as of November 2, 2026: Entergy Louisiana application to the LPSC of March 2026; a settlement recommends certification; LPSC decision expected in December 2026.
Where do the facts come from?
From the sources listed on this page, each opened and read on November 23, 2026. In March 2026 Entergy Louisiana signed a service agreement with Evest LLC, a Meta subsidiary, and applied to build seven combined cycle units totaling 5,278 MW, four near the customer site in Richland Parish and three in Pointe Coupee Parish (Entergy, Form 10-Q, November 2, 2026).
Join the takeover
Watch the plants with us
Found a newer permit or filing for this plant? Bring it to the $SIS Telegram with its link.