The Queue · MISO

The queue at MISO

MISO counts the large loads its members connect through expedited transmission reviews. The yearly total went from 0.1 GW in 2020 to 9.7 GW in 2025, and MISO projected 26.4 GW for 2026 as of July 8, 2026: 17.8 GW already approved and 8.6 GW more proposed.

Figures on file
7
Newest figure
Jul 8, 2026
Power Map sites inside
15
Live on Grid Watch
Yes

Over time

Where the source repeats

Each line joins one measure from one source at the dates the source gave, and nothing else. Every number keeps its own definition, date and source. Figures with different definitions are never added together, and a chart joins only the same measure from the same source.

Large load additions in expedited project reviews
GW02.557.510202020212022202320242025
  • Large load additions in expedited project reviews, GW, each dot a date the source gave

Every figure

MISO, figure by figure

Newest first. Each card opens its source document.

Entergy Louisiana, inside MISO, is building three gas plants certified to serve one Meta data center and has asked to build seven more for a second one. They are on Onsite Power Watch.

Every MISO figure on The Queue, newest first
FigureAmountStageAs ofSource
Projected for 2026 (17.8 GW approved, 8.6 GW proposed)26.4 GWIn studyJuly 8, 2026MISO
Large load additions in expedited project reviews9.7 GWApproved2025MISO
Large load additions in expedited project reviews2.7 GWApproved2024MISO
Large load additions in expedited project reviews900 MWApproved2023MISO
Large load additions in expedited project reviews300 MWApproved2022MISO
Large load additions in expedited project reviews200 MWApproved2021MISO
Large load additions in expedited project reviews100 MWApproved2020MISO

On the Power Map

SI data centers inside MISO

Each card opens the site on the Power Map. Status and power are Epoch AI's, read November 10, 2026.

The Power Map

Operating, expanding

Colossus 2

Memphis, Tennessee

946 MW of IT power

As of Jun 15, 2026, Epoch AI

On the Power Map

Operating, expanding

Microsoft Fairwater Wisconsin

Mount Pleasant, Wisconsin

369 MW of IT power

As of May 15, 2026, Epoch AI

On the Power Map

Operating, expanding

Amazon Madison Mega Site

Canton, Mississippi

284 MW of IT power

As of Jun 4, 2026, Epoch AI

On the Power Map

Operating

Google Council Bluffs (East)

Council Bluffs, Iowa

237 MW of IT power

On the map inside: MISO, SPP

As of Jul 7, 2026, Epoch AI

On the Power Map

Operating, expanding

Amazon Ridgeland

Ridgeland, Mississippi

228 MW of IT power

As of May 15, 2026, Epoch AI

On the Power Map

Operating

Microsoft Project Osmium

Cumming, Iowa

190 MW of IT power

As of Jun 16, 2026, Epoch AI

On the Power Map

Operating

Meta Jeffersonville

Jeffersonville, Indiana

178 MW of IT power

As of Jun 4, 2026, Epoch AI

On the Power Map

Operating

Meta Rosemount

Rosemount, Minnesota

178 MW of IT power

As of Jun 19, 2026, Epoch AI

On the Power Map

Operating, expanding

CoreWeave Ellendale ND

Ellendale, North Dakota

68 MW of IT power

On the map inside: MISO, SPP

As of Jun 30, 2026, Epoch AI

On the Power Map

Under construction

Google Cedar Rapids

Cedar Rapids, Iowa

No building running yet

As of Apr 16, 2026, Epoch AI

On the Power Map

Under construction

Meta Hyperion

Holly Ridge, Louisiana

No building running yet

As of Apr 19, 2026, Epoch AI

On the Power Map

Under construction

OpenAI Stargate Michigan

Benton, Michigan

No building running yet

As of Mar 12, 2026, Epoch AI

On the Power Map

Under construction

OpenAI Stargate Milam

Burlington, Texas

No building running yet

On the map inside: ERCOT, MISO

As of Mar 23, 2026, Epoch AI

On the Power Map

Under construction

OpenAI Stargate Wisconsin

Port Washington, Wisconsin

No building running yet

As of Jul 24, 2026, Epoch AI

On the Power Map

Under construction

QTS Cedar Rapids

Cedar Rapids, Iowa

No building running yet

As of Oct 23, 2026, Epoch AI

On the Power Map

15 Power Map sites fall inside this grid's area on the federal Control Areas map (HIFLD Open, year 2018 boundaries). 3 of them sit where the map draws two areas over the same spot; they are listed under each. A site's place on that map is a guide, not proof of which utility serves it.

Sources

Where every figure comes from

Each source was opened and read on November 23, 2026.

  • validated May 15, 2020, read Nov 23, 2026

    U.S. Department of Homeland Security, HIFLD Open (public copy)

    Control Areas (balancing authority areas), sourced from FERC 714, EIA 860 and EIA 861, year 2018

    Open the source

  • Feb 19, 2026, read Nov 23, 2026

    Entergy

    Annual report for 2025 (SEC Form 10-K)

    Open the source

  • Aug 19, 2026, read Nov 23, 2026

    MISO

    MISO Status Update to the Missouri Public Service Commission

    Open the source

  • Nov 2, 2026, read Nov 23, 2026

    Entergy

    Quarterly report for the quarter ended September 30, 2026 (SEC Form 10-Q)

    Open the source

  • retrieved Nov 10, 2026

    Epoch AI

    The Power Map's site list, towns, status and power come from Epoch AI's open data set of data centers, licensed CC BY 4.0.

    Open the source

Questions

MISO, answered

The figures, the stages and the limits.

How much power are data centers asking MISO for?

MISO counts the large loads its members connect through expedited transmission reviews. The yearly total went from 0.1 GW in 2020 to 9.7 GW in 2025, and MISO projected 26.4 GW for 2026 as of July 8, 2026: 17.8 GW already approved and 8.6 GW more proposed. Each figure on this page has its own definition and date; figures with different definitions are never added together.

Is all of that going to be built?

No figure here says what will be built. Requests are what customers asked for; many requests are speculative, duplicated across grids or withdrawn. The stages on this page (asked for, in study, approved, under contract, running) are the source's own words.

Which data centers are inside MISO?

The Power Map lists 15 sites inside MISO's area on the federal Control Areas map. See the list below; each links to its page.

Where do the figures come from?

From the grid operator's own board decks, filings and reports, each read on November 23, 2026. The links are on every figure.

How hard is MISO running right now?

Grid Watch shows MISO's demand hour by hour from the EIA, against its own forecast and its record.

Join the takeover

Read the queue with us

Open a source, check a figure yourself and bring what you find to the $SIS Telegram.