1. Home
  2. Grid Watch

Grid Watch · EIA hourly grid data

The grids, hour by hour

Grid Watch shows the live strain on the five US grids that host 56 of the 77 US sites on the Power Map: demand each hour against the grid's own forecast and its record in the EIA's hourly data. In the hour ending 10 p.m. UTC on Nov 23, 2026, MISO ran closest to its record, at 64.9%. Beside each grid: its published rule for cutting large loads in an emergency, and this winter's notices from the operator itself. No forecasts of our own, no blame.

Grids watched
5
Power Map sites inside
56
Notices this winter
1
Emergencies this winter
0

Live

Five grids, the last 72 hours

Demand each hour (solid) and the grid's own day-ahead forecast (dashed), in megawatts, with the share of its record. Hours are hour ending, shown in the grid's own time.

Snapshot built in: EIA hourly data read November 23, 2026, 23:27 UTC. The page asks the server for a newer reading when it opens.

Texas

ERCOT

the hour ending 4 p.m. CST on Nov 23, 2026

Demand, latest hour
51,166 MW
Against its forecast
-0.1%
Share of its record
56.2%
Peak so far today
53,639 MW
42.5k45k47.5k50k52.5k55kNov 21Nov 22Nov 23
  • Demand, MW, hour ending
  • The grid's day-ahead forecast

Record in the EIA's hourly data: 91,075 MW, the hour ending 6 p.m. CDT on Jul 22, 2026. The EIA reported ERCOT's summer 2026 peak of 91.1 GW on July 22, 2026 as a record in its hourly data. ERCOT's own record, measured its own way, is 91,155 MW on July 22, 2026.

Texas: Senate Bill 6

ERCOT on The Queue

Mid-Atlantic and Midwest

PJM

the hour ending 5 p.m. EST on Nov 23, 2026

Demand, latest hour
94,927 MW
Against its forecast
-4.1%
Share of its record
58.4%
Peak so far today
94,927 MW
70k80k90k100kNov 21Nov 22Nov 23
  • Demand, MW, hour ending
  • The grid's day-ahead forecast

Record in the EIA's hourly data: 162,648 MW, the hour ending 6 p.m. EDT on Jul 2, 2026. The EIA reported PJM's peak of 162.6 GW on July 2, 2026 as a record in its hourly data.

PJM: Interim Resource Adequacy Service

PJM on The Queue

Midcontinent

MISO

the hour ending 4 p.m. CST on Nov 23, 2026

Demand, latest hour
78,875 MW
Against its forecast
+1.1%
Share of its record
64.9%
Peak so far today
80,419 MW
55k60k65k70k75k80k85kNov 21Nov 22Nov 23
  • Demand, MW, hour ending
  • The grid's day-ahead forecast

Record in the EIA's hourly data: 121,514 MW, the hour ending 5 p.m. CDT on Jun 30, 2026. The EIA reported MISO's 121.5 GW on June 30, 2026 as the highest in its Hourly Electric Grid Monitor. MISO's own all time peak, 127.1 GW on July 20, 2011, predates the EIA's hourly collection.

MISO

MISO on The Queue

Central United States

SPP

the hour ending 4 p.m. CST on Nov 23, 2026

Demand, latest hour
33,481 MW
Against its forecast
-1.7%
Share of its record
57.8%
Peak so far today
35,983 MW
26k28k30k32k34k36k38kNov 21Nov 22Nov 23
  • Demand, MW, hour ending
  • The grid's day-ahead forecast

Record in the EIA's hourly data: 57,964 MW, the hour ending 5 p.m. CDT on Jul 27, 2026. The EIA reported SPP's peak of 58.0 GW on July 27, 2026 as a record in its hourly data.

SPP: conditional service for large loads (CHILLS)

SPP on The Queue

New York

NYISO

the hour ending 5 p.m. EST on Nov 23, 2026

Demand, latest hour
17,916 MW
Against its forecast
+1.8%
Share of its record
56.2%
Peak so far today
17,916 MW
12k14k16k18k20kNov 21Nov 22Nov 23
  • Demand, MW, hour ending
  • The grid's day-ahead forecast

Record in the EIA's hourly data: 31,857 MW, the hour ending 7 p.m. EDT on Jun 24, 2025. The EIA put NYISO's record in its hourly data at 31.9 GW on June 24, 2025. NYISO's own record, 34.0 GW in 2013, predates the EIA's hourly collection.

NYISO

NYISO on The Queue

The rules

Who can be cut first in an emergency

Each grid's published rule for large loads, in its own words, with its source. Not legal advice.

Texas: Senate Bill 6 · Jun 20, 2025

Loads of 75 MW or more that connect to the ERCOT grid after December 31, 2025 must have a protocol, with the equipment installed before they connect, that lets their utility curtail them during firm load shed. Critical industrial loads and critical gas facilities are exempt (Utilities Code Sec. 39.170(a)).

Large loads must tell their utility about onsite backup generation that can serve at least half of their demand. Before or during an energy emergency alert, once all market services are deployed, ERCOT may direct those loads to switch to their backup generation or curtail (Sec. 39.169(e)).

The Public Utility Commission must also set up a paid service that buys demand reductions from loads of 75 MW or more in anticipated emergencies, with at least 24 hours' notice (Sec. 39.170(b)).

Texas Legislature, Jun 20, 2025 · Utility Dive, Jun 25, 2025

Open the rule

PJM: Interim Resource Adequacy Service · Jul 27, 2026

In January 2026 the PJM Board found it reasonable for certain large loads, including data centers, to move to backup generators or curtail for a limited number of hours a year when PJM invokes its emergency procedures, to prevent a larger outage for homes and other customers. Which loads are curtailed rests with the transmission owners and load serving entities.

In July 2026 the Board decided that new large loads which, as of June 1, 2027, do not bring enough capacity will take an Interim Resource Adequacy Service, with load reductions coming before Pre-Emergency Load Management and a FERC approved compensation rate. The proposal goes to FERC.

PJM Board, Jan 16, 2026 · PJM Board, Jul 27, 2026

Open the rule

SPP: conditional service for large loads (CHILLS) · Jun 8, 2026

FERC approved SPP's conditional high impact large load service in June 2026. It lets new large loads connect sooner on available transmission for up to seven years while they obtain firm service, and SPP can cut their service when the transmission system is constrained or in emergency conditions.

Utility Dive, Jun 8, 2026

Open the rule

MISO · Aug 19, 2026

Grid Watch has found no published MISO rule that curtails large loads before other customers in an emergency. MISO's August 2026 update lists flexible large load service and FERC's show cause order on large loads as work under way. It is on the monthly recheck list.

MISO, Aug 19, 2026

Open the rule

NYISO · Jun 7, 2026

Grid Watch has found no published NYISO rule that curtails large loads before other customers in an emergency. Power Trends 2026 notes that some large loads can reduce use in times of stress. It is on the monthly recheck list.

NYISO, Jun 7, 2026

Open the rule

This winter

A plain log of the grids' notices

From the operators' own public pages since November 1, 2026: ERCOT, PJM and SPP are read by the server every hour. Only notices about supply and demand are kept, not market or local transmission ones.

Notices from the grid operators since November 1, 2026, newest first
WhenGridNoticeWhat it saysLevel
Nov 23, 5:00 p.m. CSTSPPResource AdvisorySPP is declaring a Resource Advisory for the East Balancing Authority Area (BAA) to take effect Tuesday, November 24, at 4 a.m. CT, until an anticipated end time of Wednesday, November 25, at 9 a.m. CT.Advisory

MISO's and NYISO's notice pages are not read automatically yet (MISO's page refused automated reads on November 23, 2026); they are on the monthly recheck list. Open them: MISO real-time notifications, NYISO dashboard.

Telegram

An alert when a grid declares an emergency

One short message to the $SIS Telegram channel per new emergency notice, written from the notice and the EIA data, never a forecast.

What triggers it

A new notice at emergency level: an energy emergency alert in ERCOT, a capacity emergency, load management or load shed posting in PJM, or an energy emergency alert from SPP.

The log

What it says

The grid, the time, the notice in the operator's words, the grid's latest hour against its record, its rule for large loads, and the link to the operator's notice.

The rules

Where it goes

The Telegram channel the Launch Desk already posts to, once its keys are set, through the same bot. At most three posts an hour, and never on X.

The $SIS Telegram

The record of alerts

Every alert written is listed in a public JSON with the time it was written and whether it was posted.

The alerts JSON

Method

How Grid Watch reads the grids

Free public data, no key, read about once an hour.

The data

The EIA's hourly grid data (Form EIA-930): each grid's demand and its own day-ahead forecast, hour ending, in UTC. The same data the EIA's Hourly Electric Grid Monitor draws.

The EIA monitor

The checks

An hour is left out when it is zero or less, more than one and a half times the record, or a lone spike or dip against both of its neighbors. The EIA data has had such hours.

The grids

The record

The record is the highest hour in the EIA's hourly data, as the EIA reported it in October 2026. A new hour above it that passes the checks becomes the record.

The EIA report

The grids

The five grids that hold the most Power Map sites and whose record the EIA states. Southern Company and TVA (8 sites) join when a record on the same footing is published.

The Queue

Public JSON, any origin, no key

The grids now
https://sicto.si/api/sis-grid.php?a=now72 hours of demand and forecast per grid, the latest hour, the record and the share of it.
The notices
https://sicto.si/api/sis-grid.php?a=noticesThis winter's notices from the operators, newest first.
The snapshot
https://siscto.si/assets/data/grid-watch.jsonThe data this release was built with.

Sources

Where every fact comes from

Each source was opened and read on November 23, 2026.

  • live, read Nov 23, 2026, read Nov 23, 2026

    U.S. Energy Information Administration

    Hourly Electric Grid Monitor (Form EIA-930)

    Open the source

  • Oct 15, 2026, read Nov 23, 2026

    U.S. Energy Information Administration

    PJM, ERCOT, and SWPP all set peak load records this summer (Today in Energy)

    Open the source

  • Nov 6, 2026, read Nov 23, 2026

    ERCOT

    2026 Peak Demand Records

    Open the source

  • Jun 20, 2025, read Nov 23, 2026

    Texas Legislature

    S.B. No. 6, 89th Legislature, enrolled version (Utilities Code Sec. 39.169 and 39.170)

    Open the source

  • Jun 25, 2025, read Nov 23, 2026

    Utility Dive

    Texas law gives grid operator power to disconnect data centers during crisis

    Open the source

  • Jan 16, 2026, read Nov 23, 2026

    PJM Board

    Letter on the results of the Critical Issue Fast Path process on large load additions

    Open the source

  • Jul 27, 2026, read Nov 23, 2026

    PJM Board

    Decisional letter on the Reliability Backstop Procurement and Connect and Manage

    Open the source

  • Jun 8, 2026, read Nov 23, 2026

    Utility Dive

    FERC approves SPP non-firm, large-load transmission service

    Open the source

  • Nov 23, 2026, read Nov 23, 2026

    ERCOT

    Operations Messages

    Open the source

  • Nov 23, 2026, read Nov 23, 2026

    ERCOT

    Grid conditions (the public dashboard data)

    Open the source

  • Nov 23, 2026, read Nov 23, 2026

    PJM

    Emergency Procedures: postings

    Open the source

  • Nov 23, 2026, read Nov 23, 2026

    SPP

    Current Grid Conditions

    Open the source

  • validated May 15, 2020, read Nov 23, 2026

    U.S. Department of Homeland Security, HIFLD Open (public copy)

    Control Areas (balancing authority areas), sourced from FERC 714, EIA 860 and EIA 861, year 2018

    Open the source

Every month

The monthly recheck list

What is read again each month, and what is still missing.

  • Southern Company and TVA

    A record on the same footing as the EIA's, so they can join Grid Watch (they host 8 Power Map sites).

    Where to look

  • MISO and NYISO notices

    A notice feed the server can read (MISO's page refused automated reads on November 23, 2026).

    Where to look

  • Rules

    MISO and NYISO rules for large loads in emergencies; ERCOT's implementation of Senate Bill 6.

    Where to look

Questions

Grid Watch, answered

The data, the record, the rules and the limits.

What is Grid Watch?

A live view of the strain on the five US grids that host most of the SI data centers on the Power Map: hourly demand against the grid's own forecast and against its record in the EIA's hourly data, the published rules for cutting large loads in an emergency, and a plain log of this winter's notices from the grid operators themselves.

Where do the numbers come from?

From the U.S. Energy Information Administration's hourly grid data (Form EIA-930): each grid reports its demand and its own day-ahead forecast every hour. The server reads the same free data the EIA's Hourly Electric Grid Monitor shows, with no key, about once an hour.

What is the record?

The highest hour of demand in the EIA's hourly data for that grid, which the EIA itself reported in October 2026 (it holds data from 2019 on). Some operators keep their own records, measured their own way; those are named beside it. If a new hour beats the record and passes the checks, the page moves the record and says it was found by the reader.

Do data centers or homes go dark first?

Grid Watch does not answer that for any event and blames no one. It shows each grid's published rule: in Texas, large loads of 75 MW or more that connected after 2025 can be curtailed during firm load shed, and PJM and SPP have their own rules, linked on this page.

Why is a number missing or old?

If the EIA does not answer, the page keeps showing the last good reading, or the snapshot the site was built with, with its date. Hours that cannot be real (zero, or far above the record, or a lone spike) are left out, so a grid can show its last good hour.

Is there a Telegram alert?

Yes. When a grid operator posts a new emergency notice, Grid Watch writes one short alert with the notice, the grid's latest hour and its rule, and posts it to the $SIS Telegram channel. It never posts a forecast or a guess.

Join the takeover

Watch the grids with us

Join the $SIS Telegram for the alerts, and bring any notice we missed with its link.