The Queue · grid operators and utilities
The Queue lines up how much power data centers are asking the US grids and the big utilities for, from each one's own documents. In Texas, ERCOT's count of large load requests went from 63 GW in December 2024 to about 474 GW in June 2026. AEP reported 84 GW of new load under signed agreements by 2031 in October 2026. Every number keeps its own definition and date, and none are added together.
Grid by grid
Each card shows the grid's newest count of what is asked for, or its newest figure where it publishes no count of requests. Open a grid for every figure, its line over time and the Power Map sites inside it.
Electric Reliability Council of Texas
about 474 GWAsked for, June 2026
Large load interconnection requests
PJM Interconnection
about 30 GWForecast, November 24, 2025
Data center growth PJM's review supports, 2025 to 2030
Midcontinent Independent System Operator
26.4 GWIn study, July 8, 2026
Projected for 2026 (17.8 GW approved, 8.6 GW proposed)
Southwest Power Pool
3,871 MWAsked for, August 19, 2026
HILL requests in Missouri
New York Independent System Operator
about 12.7 GWAsked for, May 1, 2026
Large load projects in the interconnection queue
The Southeast, where utilities run their own grids
about 16 GWUnder contract, September 30, 2026
Southern Company: large load contracts reviewed by the state commissions
Every number keeps its own definition, date and source. Figures with different definitions are never added together, and a chart joins only the same measure from the same source.
Utilities
From the companies' own filings with the SEC and their own presentations to the grid operator. Each card opens the grid page with the figure.
American Electric Power (AEP)
AEP reports, each quarter, the new load backed by signed customer agreements across its companies in PJM, SPP and ERCOT. The count went from 24 GW in July 2025 to 69 GW through 2030 in July 2026, and to 84 GW by 2031 in October 2026.
Dominion Energy · PJM
about 54 GWUnder contract, September 29, 2026
Data center capacity under contract. Capacity under contract at three stages (engineering letters of authorization, construction letters of authorization and electric service agreements), as Dominion told PJM. Dominion excludes 19 GW of the engineering stage from its own forecast.
On the PJM pageDominion Energy · PJM
4.8 GWRunning, August 2026
Data center billing peak load. The peak billing load of the data centers Dominion serves, as of August 2026, in the same presentation. Load that runs today, unlike the contracts above.
On the PJM pageSouthern Company · Southeast
about 16 GWUnder contract, September 30, 2026
Large load contracts reviewed by the state commissions. Contracts since 2023 with new data centers and other large load customers, each over 100 MW, reviewed by the applicable state public service commission.
On the Southeast pageSouthern Company · Southeast
about 4 GWUnder contract, September 30, 2026
Contracts agreed, under commission review. Additional contracts agreed with customers and still subject to review by the state commission. Southern Company itself calls the two together about 20 GW of Large Load Contracts, ramping up through 2029.
On the Southeast pageMethod
Read by hand from public documents, dated, linked, and never added across definitions.
Each grid operator's own board decks, filings and reports, and each utility's own filings with the SEC. News reports are used only for context, never for a figure.
Asked for, in study, approved, under contract, running, forecast: the stage each source names. A figure keeps the words its source uses.
A chart joins the same measure from the same source at three or more dates. When a source changes what it counts, the new figure starts on its own.
Power Map sites are placed in a grid by where their coordinates fall on the federal Control Areas map. Sites where two areas overlap are listed under each.
Every month
What is read again each month, and what is still missing.
ERCOT
The Batch Zero verification and community impact reports due December 10, 2026, and each monthly large load update.
PJM
The 2027 load forecast (due January 2027) and the large load adjustment requests behind it.
MISO
The MTEP26 expedited project reviews, and a large load count for all of MISO.
SPP
A count of High Impact Large Load requests for all of SPP, not only Missouri.
CAISO and ISO New England
A published count of large load or data center requests (none read yet; no Power Map site lies in either grid).
Utilities
Each quarter's filings from AEP, Southern Company and Entergy, and whether Duke Energy, Xcel Energy and others publish a gigawatt figure.
Public JSON, any origin, no key
Sources
Each source was opened and read on November 23, 2026.
Jul 30, 2025, read Nov 23, 2026
Second-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)
Oct 29, 2025, read Nov 23, 2026
Third-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)
Feb 12, 2026, read Nov 23, 2026
Fourth-quarter and full-year 2025 earnings release (SEC Form 8-K, exhibit 99.1)
May 5, 2026, read Nov 23, 2026
First-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)
Jul 30, 2026, read Nov 23, 2026
Second-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)
Oct 28, 2026, read Nov 23, 2026
Third-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)
Sep 29, 2026, read Nov 23, 2026
Dominion Energy LSE 20-Year Data Center Forecast, Load Analysis Subcommittee
Dec 19, 2025, read Nov 23, 2026
ERCOT Monthly, November 2025: Large Load Interconnection Requests Update
Feb 25, 2026, read Nov 23, 2026
Large Load Interconnection Status Update to the Technical Advisory Committee
Apr 13, 2026, read Nov 23, 2026
Item 9: Interconnection and Grid Analysis Update, Board of Directors
May 24, 2026, read Nov 23, 2026
Item 8: Interconnection and Grid Analysis Update, Board of Directors, June 1 to 2, 2026
Jul 29, 2026, read Nov 23, 2026
ERCOT update to the Texas Senate, July 29, 2026: Assessing the grid
Aug 19, 2026, read Nov 23, 2026
ERCOT update to the Texas House Committee on State Affairs, August 19, 2026
Sep 11, 2026, read Nov 23, 2026
Item 14: Batch Zero Update, Board of Directors, September 14 to 15, 2026
Nov 5, 2026, read Nov 23, 2026
Data Center State and Community Impact RFI: Preliminary Summary, PUC Open Meeting
Feb 19, 2026, read Nov 23, 2026
Annual report for 2025 (SEC Form 10-K)
Nov 2, 2026, read Nov 23, 2026
Quarterly report for the quarter ended September 30, 2026 (SEC Form 10-Q)
Aug 19, 2026, read Nov 23, 2026
MISO Status Update to the Missouri Public Service Commission
Aug 26, 2025, read Nov 23, 2026
Energy-Intensive Projects in NYISO's Interconnection Queue
Jun 7, 2026, read Nov 23, 2026
Power Trends 2026
Nov 24, 2025, read Nov 23, 2026
Load Adjustment Requests Summary for the 2026 Load Forecast, Load Analysis Subcommittee
Jan 14, 2026, read Nov 23, 2026
2026 PJM Load Forecast Report
Aug 19, 2026, read Nov 23, 2026
SPP Status Update to the Missouri Public Service Commission
Nov 5, 2026, read Nov 23, 2026
Quarterly report for the quarter ended September 30, 2026 (SEC Form 10-Q)
The set
Each reads a different public record of the same sites and grids.
Every SI data center public data can confirm, with its power.
Open the mapWhat was announced against what is confirmed energized.
Read the LedgerThe plants built to run data centers directly.
See the plantsLive demand on the grids that host the most sites.
Watch the gridsHome power prices in every state with a site.
Read the billQuestions
The figures, the definitions and the limits.
A free record of how much power SI data centers and other large loads are asking each US grid and the big utilities for, figure by figure: requests, studies, approvals, contracts and load already running, from each grid operator's own board decks and reports and each utility's own filings. Each figure keeps its own definition, date and link.
Because the grids and utilities count different things. One counts every request, another only loads in a study, another contracts at three stages. Adding them would mix definitions and count the same project twice, since developers ask several grids at once. Every number keeps its own definition, date and source. Figures with different definitions are never added together, and a chart joins only the same measure from the same source.
No. A request is what a customer asked for. Many are speculative or duplicated, and grids now ask for proof before they study them. In Texas, ERCOT tracked about 474 GW of requests in June 2026; the narrower group eligible for its first batch study was about 205 GW in July 2026.
The figures are read by hand from the sources and rechecked every month, on the list on this page. The figures here were read on November 23, 2026. A new figure is added with its own date; an old one stays, so the history shows.
Yes. Every figure is a fact from a public document, linked to it. The whole set is a free download at /assets/data/the-queue.json, and a public JSON answers at https://sicto.si/api/sis-queue.php?a=list for any origin, with no key. Link this page and the sources.