1. Home
  2. The Queue

The Queue · grid operators and utilities

The power data centers ask for

The Queue lines up how much power data centers are asking the US grids and the big utilities for, from each one's own documents. In Texas, ERCOT's count of large load requests went from 63 GW in December 2024 to about 474 GW in June 2026. AEP reported 84 GW of new load under signed agreements by 2031 in October 2026. Every number keeps its own definition and date, and none are added together.

Grids tracked
6
Utilities tracked
3
Figures on file
36
Newest figure
Nov 5, 2026

Utilities

What the utilities say they have signed

From the companies' own filings with the SEC and their own presentations to the grid operator. Each card opens the grid page with the figure.

American Electric Power (AEP)

AEP reports, each quarter, the new load backed by signed customer agreements across its companies in PJM, SPP and ERCOT. The count went from 24 GW in July 2025 to 69 GW through 2030 in July 2026, and to 84 GW by 2031 in October 2026.

New load by 2030 under customer agreements
GW020406080Jul 2025Oct 2025Feb 2026May 2026Jul 2026
  • New load by 2030 under customer agreements, GW, each dot a date the source gave

On the pages of PJM, SPP, ERCOT, with every figure.

Dominion Energy · PJM

about 54 GWUnder contract, September 29, 2026

Data center capacity under contract. Capacity under contract at three stages (engineering letters of authorization, construction letters of authorization and electric service agreements), as Dominion told PJM. Dominion excludes 19 GW of the engineering stage from its own forecast.

On the PJM page

Dominion Energy · PJM

4.8 GWRunning, August 2026

Data center billing peak load. The peak billing load of the data centers Dominion serves, as of August 2026, in the same presentation. Load that runs today, unlike the contracts above.

On the PJM page

Southern Company · Southeast

about 16 GWUnder contract, September 30, 2026

Large load contracts reviewed by the state commissions. Contracts since 2023 with new data centers and other large load customers, each over 100 MW, reviewed by the applicable state public service commission.

On the Southeast page

Southern Company · Southeast

about 4 GWUnder contract, September 30, 2026

Contracts agreed, under commission review. Additional contracts agreed with customers and still subject to review by the state commission. Southern Company itself calls the two together about 20 GW of Large Load Contracts, ramping up through 2029.

On the Southeast page

Method

How The Queue is made

Read by hand from public documents, dated, linked, and never added across definitions.

The sources

Each grid operator's own board decks, filings and reports, and each utility's own filings with the SEC. News reports are used only for context, never for a figure.

Every source

The stages

Asked for, in study, approved, under contract, running, forecast: the stage each source names. A figure keeps the words its source uses.

ERCOT, every stage

The lines

A chart joins the same measure from the same source at three or more dates. When a source changes what it counts, the new figure starts on its own.

MISO by year

The sites

Power Map sites are placed in a grid by where their coordinates fall on the federal Control Areas map. Sites where two areas overlap are listed under each.

The Power Map

Every month

The monthly recheck list

What is read again each month, and what is still missing.

  • ERCOT

    The Batch Zero verification and community impact reports due December 10, 2026, and each monthly large load update.

    Where to look

  • PJM

    The 2027 load forecast (due January 2027) and the large load adjustment requests behind it.

    Where to look

  • MISO

    The MTEP26 expedited project reviews, and a large load count for all of MISO.

    Where to look

  • SPP

    A count of High Impact Large Load requests for all of SPP, not only Missouri.

    Where to look

  • CAISO and ISO New England

    A published count of large load or data center requests (none read yet; no Power Map site lies in either grid).

    Where to look

  • Utilities

    Each quarter's filings from AEP, Southern Company and Entergy, and whether Duke Energy, Xcel Energy and others publish a gigawatt figure.

    Where to look

Public JSON, any origin, no key

Every grid
https://sicto.si/api/sis-queue.php?a=listEach grid and utility with its newest figure.
One grid
https://sicto.si/api/sis-queue.php?a=grid&g=ercotEvery figure with its definition, date and source.
The whole set
https://siscto.si/assets/data/the-queue.jsonOne file with every figure and source, as built into this release.

Sources

Where every figure comes from

Each source was opened and read on November 23, 2026.

  • Jul 30, 2025, read Nov 23, 2026

    AEP

    Second-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)

    Open the source

  • Oct 29, 2025, read Nov 23, 2026

    AEP

    Third-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)

    Open the source

  • Feb 12, 2026, read Nov 23, 2026

    AEP

    Fourth-quarter and full-year 2025 earnings release (SEC Form 8-K, exhibit 99.1)

    Open the source

  • May 5, 2026, read Nov 23, 2026

    AEP

    First-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)

    Open the source

  • Jul 30, 2026, read Nov 23, 2026

    AEP

    Second-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)

    Open the source

  • Oct 28, 2026, read Nov 23, 2026

    AEP

    Third-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)

    Open the source

  • Sep 29, 2026, read Nov 23, 2026

    Dominion Energy, to PJM

    Dominion Energy LSE 20-Year Data Center Forecast, Load Analysis Subcommittee

    Open the source

  • Dec 19, 2025, read Nov 23, 2026

    ERCOT

    ERCOT Monthly, November 2025: Large Load Interconnection Requests Update

    Open the source

  • Feb 25, 2026, read Nov 23, 2026

    ERCOT

    Large Load Interconnection Status Update to the Technical Advisory Committee

    Open the source

  • Apr 13, 2026, read Nov 23, 2026

    ERCOT

    Item 9: Interconnection and Grid Analysis Update, Board of Directors

    Open the source

  • May 24, 2026, read Nov 23, 2026

    ERCOT

    Item 8: Interconnection and Grid Analysis Update, Board of Directors, June 1 to 2, 2026

    Open the source

  • Jul 29, 2026, read Nov 23, 2026

    ERCOT

    ERCOT update to the Texas Senate, July 29, 2026: Assessing the grid

    Open the source

  • Aug 19, 2026, read Nov 23, 2026

    ERCOT

    ERCOT update to the Texas House Committee on State Affairs, August 19, 2026

    Open the source

  • Sep 11, 2026, read Nov 23, 2026

    ERCOT

    Item 14: Batch Zero Update, Board of Directors, September 14 to 15, 2026

    Open the source

  • Nov 5, 2026, read Nov 23, 2026

    ERCOT

    Data Center State and Community Impact RFI: Preliminary Summary, PUC Open Meeting

    Open the source

  • Feb 19, 2026, read Nov 23, 2026

    Entergy

    Annual report for 2025 (SEC Form 10-K)

    Open the source

  • Nov 2, 2026, read Nov 23, 2026

    Entergy

    Quarterly report for the quarter ended September 30, 2026 (SEC Form 10-Q)

    Open the source

  • Aug 19, 2026, read Nov 23, 2026

    MISO

    MISO Status Update to the Missouri Public Service Commission

    Open the source

  • Aug 26, 2025, read Nov 23, 2026

    NYISO

    Energy-Intensive Projects in NYISO's Interconnection Queue

    Open the source

  • Jun 7, 2026, read Nov 23, 2026

    NYISO

    Power Trends 2026

    Open the source

  • Nov 24, 2025, read Nov 23, 2026

    PJM

    Load Adjustment Requests Summary for the 2026 Load Forecast, Load Analysis Subcommittee

    Open the source

  • Jan 14, 2026, read Nov 23, 2026

    PJM

    2026 PJM Load Forecast Report

    Open the source

  • Aug 19, 2026, read Nov 23, 2026

    SPP

    SPP Status Update to the Missouri Public Service Commission

    Open the source

  • Nov 5, 2026, read Nov 23, 2026

    Southern Company

    Quarterly report for the quarter ended September 30, 2026 (SEC Form 10-Q)

    Open the source

Questions

The Queue, answered

The figures, the definitions and the limits.

What is The Queue?

A free record of how much power SI data centers and other large loads are asking each US grid and the big utilities for, figure by figure: requests, studies, approvals, contracts and load already running, from each grid operator's own board decks and reports and each utility's own filings. Each figure keeps its own definition, date and link.

Why not one total for the whole country?

Because the grids and utilities count different things. One counts every request, another only loads in a study, another contracts at three stages. Adding them would mix definitions and count the same project twice, since developers ask several grids at once. Every number keeps its own definition, date and source. Figures with different definitions are never added together, and a chart joins only the same measure from the same source.

Does a request mean a data center will be built?

No. A request is what a customer asked for. Many are speculative or duplicated, and grids now ask for proof before they study them. In Texas, ERCOT tracked about 474 GW of requests in June 2026; the narrower group eligible for its first batch study was about 205 GW in July 2026.

How often is it updated?

The figures are read by hand from the sources and rechecked every month, on the list on this page. The figures here were read on November 23, 2026. A new figure is added with its own date; an old one stays, so the history shows.

Can I reuse the data?

Yes. Every figure is a fact from a public document, linked to it. The whole set is a free download at /assets/data/the-queue.json, and a public JSON answers at https://sicto.si/api/sis-queue.php?a=list for any origin, with no key. Link this page and the sources.

Is $SIS linked to any grid operator or utility?

$SIS is a community meme token with no affiliation with, or endorsement from, any grid operator, utility or data center company. The Queue uses their public documents and says what they show.

Join the takeover

Read the queue with us

Open a source, check a figure yourself and bring what you find to the $SIS Telegram.