Power Map · Operating, expanding
Amazon Ridgeland, Ridgeland
Amazon Ridgeland is an SI data center in Ridgeland, Mississippi, United States, owned by Amazon and used by Anthropic (Epoch AI rates this speculative). Epoch AI estimates its IT power at 228 MW as of May 15, 2026, with 4 buildings operating, and projects 840 MW by September 29, 2028. Its public timeline starts on February 24, 2024.
- IT power
- 228 MWMay 15, 2026
- Facility power
- 273 MW
- Status
- Operating, expanding
- Buildings operating
- 4
Where it is
The site and its facts
Amazon Ridgeland on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- Ridgeland, Mississippi, United States
- Address
- 1626 County Line Road Ridgeland, Mississippi
- Coordinates
- 32.4105° N, 90.1898° W
- Owner
- Amazon
- Users
- Anthropic (Epoch AI rates this speculative)
- Project
- Project Rainier
- Chips
- Trainium2
- Compute
- About 171,299 H100 equivalentsEpoch AI estimate, May 15, 2026
- Energy
- Entergy
- Projected
- 840 MW IT power by September 29, 2028Epoch AI projection, not a fact yet
Heat Watch
Amazon Ridgeland: heat seen from space
Over the last three summers NASA's MODIS read the ground here -0.9 °C against the land 5 to 10 km around it by day.
Lights On
Amazon Ridgeland: light at night
NASA's night imagery read 39.2 of 100 over this site in October 2026, against 17.1 in October 2018, the first month read. Against a year before: +9.5 points. The place was already bright at the first reading, so growth is harder to see. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on Amazon Ridgeland, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
Land clearing begins
No IT power yet0 operating
Roof complete on Buildings 3
No IT power yet0 operating
Buildings 1-4 are operational, based on the buildings shells and backup generators and most of the landscaping looking complete. Building 5 roof is complete but still lacks cooling equipment.
228 MW4 operating
Building 5 is operational (estimate).
284 MW5 operating
Buildings 6-14 are operational (estimate). Buildings 1-4 took an estimated 2.25 years on this site. We assume Buildings 6-14 get underway by July 2026, and take the same time as Buildings 1-4. This is later than the expected completion by 2027.
840 MW14 operating
Adopt a site
Watch Amazon Ridgeland
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Air Construction Permit
- Permit review document
- Backup diesel generator referenced in the permit
- New York Times article on Project Rainier
- Epoch AI, "AI data centers", the record for Amazon Ridgeland (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
23 km away
Amazon Madison Mega Site
Canton, Mississippi, United States
284 MW IT power
136 km away
Meta Hyperion
Holly Ridge, Louisiana, United States
IT power not stated
287 km away
Colossus 2
Memphis, Tennessee, United States
946 MW IT power
295 km away
Colossus 1
Memphis, Tennessee, United States
340 MW IT power
Questions
Amazon Ridgeland, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is Amazon Ridgeland?
Amazon Ridgeland is in Ridgeland, Mississippi, United States, at 1626 County Line Road Ridgeland, Mississippi. Epoch AI publishes its coordinates as 32.4105, -90.1898.
Who owns Amazon Ridgeland?
Epoch AI lists Amazon as its owner and Anthropic (Epoch AI rates this speculative) as its user.
How much power does Amazon Ridgeland use?
Epoch AI estimates its IT power at 228 MW as of May 15, 2026, and its total facility power at 273 MW. It projects 840 MW of IT power by September 29, 2028.
Is Amazon Ridgeland operating?
Yes, and it is growing. Epoch AI counts 4 buildings operating as of May 15, 2026, with more capacity on its timeline.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).