Power Map · Operating, expanding
Anthropic Lake Mariner, Barker
Anthropic Lake Mariner is an SI data center in Barker, New York, United States, owned by AI XPV Platform and used by Anthropic (Epoch AI rates this likely). Epoch AI estimates its IT power at 210 MW as of October 31, 2026, with 2 buildings operating, and projects 378 MW by March 31, 2027. Its public timeline starts on June 11, 2025.
- IT power
- 210 MWOct 31, 2026
- Facility power
- 245 MW
- Status
- Operating, expanding
- Buildings operating
- 2
Where it is
The site and its facts
Anthropic Lake Mariner on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- Barker, New York, United States
- Address
- 7725 Lake Rd, Barker, NY 14012
- Coordinates
- 43.3564° N, 78.6020° W
- Owner
- AI XPV Platform
- Users
- Anthropic (Epoch AI rates this likely)
- Chips
- TPU v7
- Compute
- About 292,830 H100 equivalentsEpoch AI estimate, Oct 31, 2026
- Projected
- 378 MW IT power by March 31, 2027Epoch AI projection, not a fact yet
The Gigawatt Ledger · Partly energized
Lake Mariner: announced against built
440 MW was announced for this project. Public evidence puts 268 MW in operation as of October 31, 2026, against 440 MW announced: 61%. The announcement states IT load, so it is set against the IT load running.
Heat Watch
Anthropic Lake Mariner: heat seen from space
Over the last three summers NASA's MODIS read the ground here +1.2 °C against the land 5 to 10 km around it by day.
Lights On
Anthropic Lake Mariner: light at night
NASA's night imagery read 28.4 of 100 over this site in October 2026, against 2.8 in October 2018, the first month read. Against a year before: +20.6 points. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on Anthropic Lake Mariner, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
Land clearing begins for Building 1 (AKA CB3).
No IT power yet0 operating
Building 1 appears to have a complete shell and cooling equipment. Building 2 shell is still under construction, but 17 cooling units are already loaded on the roof. The outline of Building 3 is visible at the foundation.
No IT power yet0 operating
Building 1 is operational. On February 26, Terawulf stated that CB3 was expected to be energized by mid-May 2026. A drone video commissioned from RAAD shows several cooling units operating on May 8. It's therefore likely that the building was fully operational around this date.
42 MW1 operating
Building 1 looks complete, consistent with it going operational back in May. Building 2 is mostly complete, with the row of backup generators on the east side of the building still being installed. Building 3 shell is complete, with rooftop coolers midway through installation, and no neighboring generators installed/visible yet.
42 MW1 operating
Building 2 (AKA CB4) is operational. On February 26, Terawulf stated that CB4 was expected to be energized by Q3 2026.
210 MW2 operating
Building 3 (AKA CB5) is operational. On February 26, 2026, Terawulf stated that CB5 was expected to be energized by Q4 2026. However, based on the pace of Building 2, and comparisons to other projects like Stargate Abilene, we think this is optimistic. We expect a 3-month delay past the end of Q4 2026 to get to full operational capacity.
378 MW3 operating
Adopt a site
Watch Anthropic Lake Mariner
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Terawulf press release with details and timeline for Buildings 1-5
- DCD article suggesting that Fluidstack will deploy Google TPUs at Lake Mariner
- Announcement of Anthropic-Fluidstack partnership, including data center(s) in New York
- Epoch AI, "AI data centers", the record for Anthropic Lake Mariner (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
0 km away
Core42 Lake Mariner
Barker, New York, United States
58 MW IT power
309 km away
OpenAI Stargate Lordstown
Lordstown, Ohio, United States
IT power not stated
323 km away
AWS Berwick
Berwick, Pennsylvania, United States
108 MW IT power
416 km away
CoreWeave Lancaster Greenfield site
Lancaster, Pennsylvania, United States
IT power not stated
Questions
Anthropic Lake Mariner, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is Anthropic Lake Mariner?
Anthropic Lake Mariner is in Barker, New York, United States, at 7725 Lake Rd, Barker, NY 14012. Epoch AI publishes its coordinates as 43.3564, -78.6020.
Who owns Anthropic Lake Mariner?
Epoch AI lists AI XPV Platform as its owner and Anthropic (Epoch AI rates this likely) as its user.
How much power does Anthropic Lake Mariner use?
Epoch AI estimates its IT power at 210 MW as of October 31, 2026, and its total facility power at 245 MW. It projects 378 MW of IT power by March 31, 2027.
Is Anthropic Lake Mariner operating?
Yes, and it is growing. Epoch AI counts 2 buildings operating as of October 31, 2026, with more capacity on its timeline.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).