Gigawatt Ledger · Partly energized

Lake Mariner, announced against built

Lake Mariner is an SI compute project in Barker, New York, by Fluidstack, TeraWulf, Core42 and Anthropic. The announced figure is 440 critical IT MW under lease (380 MW and 60 MW), from TeraWulf (Feb 26, 2026). Public evidence puts 268 MW in operation as of October 31, 2026, against 440 MW announced: 61%. The announcement states IT load, so it is set against the IT load running. Its state today: partly energized.

Announced
440 MW
Energized
268 MWOct 31, 2026
State
Partly energized
Source links
4

Announced

What was said, and when

Each row is one public announcement about Lake Mariner: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

  1. Company statement

    Anthropic

    Anthropic invests $50 billion in American AI infrastructure

    Anthropic announces data centers with Fluidstack in Texas and New York. It names no site and states no power figure.

    “a $50 billion investment in American computing infrastructure”
    “with sites coming online throughout 2026”
    Power or capacity stated
    None stated
    Promised
    Sites online throughout 2026
  2. Company statement

    TeraWulf

    TeraWulf Reports Fourth Quarter and Full Year 2025 Results

    TeraWulf lists its leases at the Lake Mariner campus (380 critical IT MW with Fluidstack, 60 with Core42) and the date each building is expected to be energized.

    “39 critical IT MW HPC capacity online”
    “more than 500 MW of near-term contracted campus capacity”
    “Energization expected Q3 2026”
    “Energization expected Q4 2026”
    Power or capacity stated
    440 critical IT MW under lease (380 MW Fluidstack, 60 MW Core42)
    Promised
    Buildings energized from March 2026 to the fourth quarter of 2026

Built

What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Partly energized

Public evidence puts 268 MW in operation as of October 31, 2026, against 440 MW announced: 61%. The announcement states IT load, so it is set against the IT load running.

  1. Epoch AI estimate

    Epoch AI · Power Map

    Anthropic Lake Mariner on the Power Map

    Epoch AI counts 2 buildings operating at Anthropic Lake Mariner and estimates 210 MW of IT power (245 MW for the whole facility) as of October 31, 2026.

    Building 2 (AKA CB4) is operational. On February 26, Terawulf stated that CB4 was expected to be energized by Q3 2026.
    IT power running
    210 MW
    Whole facility
    245 MW

    Epoch AI projects 378 MW of IT power by March 31, 2027. A projection, not a fact yet.

  2. Epoch AI estimate

    Epoch AI · Power Map

    Core42 Lake Mariner on the Power Map

    Epoch AI counts 2 buildings operating at Core42 Lake Mariner and estimates 58 MW of IT power (58 MW for the whole facility) as of July 23, 2026.

    Both buildings still operational according to satellite imagery.
    IT power running
    58 MW
    Whole facility
    58 MW

Heat Watch

Anthropic Lake Mariner: heat seen from space

Over the last three summers NASA's MODIS read the ground here +1.2 °C against the land 5 to 10 km around it by day.

Heat Watch

Core42 Lake Mariner: heat seen from space

Over the last three summers NASA's MODIS read the ground here +1.3 °C against the land 5 to 10 km around it by day.

Timeline

Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

  1. Core42 Lake Mariner: 1 building operating, 16 MW of IT power.Evidence · Epoch AI, on the Power Map

  2. Anthropic: no power figure stated. Promised: sites online throughout 2026.Announcement · Anthropic

  3. TeraWulf: 440 critical IT MW under lease (380 MW Fluidstack, 60 MW Core42). Promised: buildings energized from March 2026 to the fourth quarter of 2026.Announcement · TeraWulf

  4. Anthropic Lake Mariner: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map

  5. Core42 Lake Mariner: 1 building operating, 16 MW of IT power.Evidence · Epoch AI, on the Power Map

  6. Core42 Lake Mariner: 2 buildings operating, 58 MW of IT power.Evidence · Epoch AI, on the Power Map

  7. Anthropic Lake Mariner: 1 building operating, 42 MW of IT power.Evidence · Epoch AI, on the Power Map

  8. Anthropic Lake Mariner: 1 building operating, 42 MW of IT power.Evidence · Epoch AI, on the Power Map

  9. Core42 Lake Mariner: 2 buildings operating, 58 MW of IT power.Evidence · Epoch AI, on the Power Map

  10. Anthropic Lake Mariner: 2 buildings operating, 210 MW of IT power.Evidence · Epoch AI, on the Power Map

Corrections

See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

File a correction

Sign in with your SI Passport to file a correction. It is a free message signature and never moves tokens.

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

  • Loading the corrections on file.

Sources

Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.