Bridge Data Centres MY06 is an SI data center in Kulai, Johor, Malaysia, owned by ByteDance (Epoch AI rates this likely) and used by ByteDance (Epoch AI rates this likely). Epoch AI estimates its IT power at 243 MW as of September 13, 2026, with 7 buildings operating. Its public timeline starts on October 1, 2021.

IT power
243 MWSep 13, 2026
Facility power
315 MW
Status
Operating
Buildings operating
7

Where it is

The site and its facts

Bridge Data Centres MY06 on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Kulai, Johor, MalaysiaOpen in OpenStreetMap
Place
Kulai, Johor, Malaysia
Address
Bridge Data Centres, Sedenak Tech Park, Johor, Malaysia
Coordinates
1.6972° N, 103.4159° E
Owner
ByteDance (Epoch AI rates this likely)
Users
ByteDance (Epoch AI rates this likely)
Chips
A100, H100, B200
Compute
About 221,052 H100 equivalentsEpoch AI estimate, Sep 13, 2026

Heat Watch

Bridge Data Centres MY06: heat seen from space

Over the last three summers NASA's MODIS read the ground here -0.6 °C against the land 5 to 10 km around it by day, a change of -0.5 °C since before work on this build began.

Lights On

Bridge Data Centres MY06: light at night

NASA's night imagery read 46.4 of 100 over this site in October 2026, against 5.4 in October 2018, the first month read. Against a year before: +12.9 points. Light is not proof of what runs inside.

Timeline

Dated, from the public record

Epoch AI's dated notes on Bridge Data Centres MY06, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

  1. Land clearing begins for campus 1, seen via satellite imagery. This start date is corroborated by the Malaysian Investment Development Authority, citing November for officially first breaking ground.

    No IT power yet0 operating

  2. Building 1 (MY06-1) is operational. The SEC filing for Chindata and local news sources reported the building was in service as of October 20, but only a subsequent filing confirmed 19 MW was utilized by December 31, so we conservatively assume December 31.

    19 MW1 operating

  3. Drone footage indicates that Building 1 is operating at full capacity, with 4 of 5 cooling tower fans spinning. Building 2 has 2 of 21 fans spinning and some ongoing construction work, so we assume it's not fully operational yet. We estimate another 3 months until full utilization.

    19 MW1 operating

  4. Building 2 (MY06-2) is operational.

    61 MW2 operating

  5. Building 3 and 4 are operational. Building 3 was originally scheduled for 2024Q4, and seemed partly operational in June, so it's likely to be fully utilized by this date. Building 4 was scheduled for delivery starting 2024Q1, but it typically takes a few more months to fit out and reach full utilization, so we think it's only fully utilized by this date. At Campus 2, Buildings 5-7 and Building 9 are close to finishing construction while Buildings 8 and 10 shells are still under construction. The Campus 2 substation looks complete.

    114 MW4 operating

  6. Construction looks complete on Building 5, 6 and 7, but we allow 3 more months for fit-out and ramping before declaring them operational.

    114 MW4 operating

  7. Buildings 5-7 are operational.

    243 MW7 operating

  8. Buildings 8 and 9 look structurally complete. The remaining building, building 10, still has construction material around it and scaffolding on the roof, with cooling units yet to be installed.

    243 MW7 operating

  9. All cooling units are now installed on Building 10. Drone footage from the same month shows most cooling units operating for Buildings 5-7, but none (or very few) for Buildings 8-10. So we don't think Buildings 8-10 are operating significantly yet.

    243 MW7 operating

  10. No visible construction work on Buildings 8-10, but no cars in their carparks either (whereas Building 7 has many cars). So we still don't think Buildings 8-10 are utilized.

    243 MW7 operating

Adopt a site

Watch Bridge Data Centres MY06

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

The watcher

Loading the watcher.

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

  • Approved updates show here with their date.

Sources

Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

Questions

Bridge Data Centres MY06, answered

Where it is, who owns it and how much power it uses, from the public record.

Where is Bridge Data Centres MY06?

Bridge Data Centres MY06 is in Kulai, Johor, Malaysia, at Bridge Data Centres, Sedenak Tech Park, Johor, Malaysia. Epoch AI publishes its coordinates as 1.6972, 103.4159.

Who owns Bridge Data Centres MY06?

Epoch AI lists ByteDance (Epoch AI rates this likely) as its owner and ByteDance (Epoch AI rates this likely) as its user.

How much power does Bridge Data Centres MY06 use?

Epoch AI estimates its IT power at 243 MW as of September 13, 2026, and its total facility power at 315 MW.

Is Bridge Data Centres MY06 operating?

Yes. Epoch AI counts 7 buildings operating as of September 13, 2026.