Power Map · Operating

DayOne Kempas, Kempas

DayOne Kempas is an SI data center in Kempas, Johor, Malaysia. Epoch AI estimates its IT power at 421.7 MW as of October 1, 2026, with 9 buildings operating. Its public timeline starts on November 11, 2023.

IT power
421.7 MWOct 1, 2026
Facility power
590.4 MW
Status
Operating
Buildings operating
9

Where it is

The site and its facts

DayOne Kempas on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Kempas, Johor, MalaysiaOpen in OpenStreetMap
Place
Kempas, Johor, Malaysia
Address
HP79+MP, 81300 Johor Bahru, Johor, Malaysia
Coordinates
1.5594° N, 103.7199° E
Owner
Not public
Chips
B300
Compute
About 480,639 H100 equivalentsEpoch AI estimate, Oct 1, 2026

Heat Watch

DayOne Kempas: heat seen from space

Over the last three summers NASA's MODIS read the ground here -1.7 °C against the land 5 to 10 km around it by day.

Lights On

DayOne Kempas: light at night

NASA's night imagery read 95.6 of 100 over this site in October 2026, against 68.7 in October 2018, the first month read. Against a year before: +11.8 points. The place was already bright at the first reading, so growth is harder to see. Light is not proof of what runs inside.

Timeline

Dated, from the public record

Epoch AI's dated notes on DayOne Kempas, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

  1. Land clearing begins.

    No IT power yet0 operating

  2. In this video at 6:28, some fans can be seen in motion for Building 3. However, we think it's unlikely that any buildings are at fully operational capacity yet. Buildings 1-4 are roofed. Building 5-6 shells are underway.

    No IT power yet0 operating

  3. Buildings 3 and 4 are operational. This is based on construction looking complete, and DayOne reporting 390 MW "in service" across both Nusajaya and Kempas campuses as of Jan 30. Subtracting our Nusajaya estimates (69.5 MW excluded in Phase 1 + 240.3 MW AI) implies ~80 MW in service at KTP, consistent with roughly 2 buildings per our ~49.6 MW per-building estimate, but not at full capacity. Buildings 1 and 2 look complete with rooftop cooling equipment installed (32 units each, in 2 strips of 16). The units are almost all single-fan cells; Building 2 has one strip of 16 single-fan cells and one darker bank of 16 long multi-fan air-cooled (slat) units - this suggests an cell-to-air-cooled power equivalence that informs our power estimates. The smaller Building 9 (west of Building 1, half fit-out: 16 cells) also has its cooling installed. Building 5 has rooftop equipment partially installed; Building 6 is roofed; Buildings 7-8 shells are still underway.

    80.2 MW2 operating

  4. Buildings 1-4 and the smaller Building 9 assumed fully operational: cooling equipment was installed by Jan 2026 (Building 9 on the same timeline as Building 1) and the implied KTP in-service figure (~80 MW) shows them ramping in early 2026, so we allow ~3 more months to reach full capacity. Rooftop equipment texture is visible campus-wide.

    223.2 MW5 operating

  5. Buildings 5-6 look complete and parking lot activity suggests they are nearly operational. Building 7-8 nearing completion with some construction equipment still in their vicinity.

    223.2 MW5 operating

  6. Buildings 5-6 assumed operational. These buildings were roofed between Sep and Dec 2025 and equipment fit-out was underway in Jan 2026; applying the default roof-to-operational delay plus ramp time approximates their operability to this date.

    322.5 MW7 operating

  7. Buildings 7-8 assumed operational. These buildings were roofed by March 2026 and by August 2026 their cooling and backup power equipment looked complete. With an additional two months of commissioning after August we approximate their operability to this date.

    421.7 MW9 operating

Adopt a site

Watch DayOne Kempas

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

The watcher

Loading the watcher.

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

  • Approved updates show here with their date.

Sources

Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

Questions

DayOne Kempas, answered

Where it is, who owns it and how much power it uses, from the public record.

Where is DayOne Kempas?

DayOne Kempas is in Kempas, Johor, Malaysia, at HP79+MP, 81300 Johor Bahru, Johor, Malaysia. Epoch AI publishes its coordinates as 1.5594, 103.7199.

Who owns DayOne Kempas?

Epoch AI does not name an owner yet.

How much power does DayOne Kempas use?

Epoch AI estimates its IT power at 421.7 MW as of October 1, 2026, and its total facility power at 590.4 MW.

Is DayOne Kempas operating?

Yes. Epoch AI counts 9 buildings operating as of October 1, 2026.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).