Power Map · Operating, expanding
YTL Johor, Kulai
YTL Johor is an SI data center in Kulai, Johor, Malaysia. Epoch AI estimates its IT power at 113 MW as of July 13, 2026, with 2 buildings operating, and projects 284 MW by August 1, 2028. Its public timeline starts on November 1, 2023.
- IT power
- 113 MWJul 13, 2026
- Facility power
- 155 MW
- Status
- Operating, expanding
- Buildings operating
- 2
Where it is
The site and its facts
YTL Johor on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- Kulai, Johor, Malaysia
- Address
- YTL Green Data Centers, Kulai, Johor, Malaysia
- Coordinates
- 1.6183° N, 103.5192° E
- Owner
- Not public
- Chips
- B200, B300
- Compute
- About 153,532 H100 equivalentsEpoch AI estimate, Jul 13, 2026
- Projected
- 284 MW IT power by August 1, 2028Epoch AI projection, not a fact yet
Heat Watch
YTL Johor: heat seen from space
Over the last three summers NASA's MODIS read the ground here +0.5 °C against the land 5 to 10 km around it by day.
Lights On
YTL Johor: light at night
NASA's night imagery read 26.3 of 100 over this site in October 2026, against 1.7 in October 2018, the first month read. Against a year before: +9.3 points. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on YTL Johor, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
Land clearing begins for Building 1.
No IT power yet0 operating
Building 1 is operational with Nvidia GB200s, according to the local investment development authority.
20 MW1 operating
Building 2 is operational, assuming 3 months to structural completion plus 3 months fit-out after this video. Solar panels are also being installed to the north west of the campus.
100 MW2 operating
Building 1 added 4 two-fan cooling towers (config 3), installed mid May of 2026. This capacity is not reflected in any disclosure (the building is still reported at 20MW IT load).
113 MW2 operating
Satellite imagery confirms Buildings 1 and 2 are structurally complete. Buildings 3 and 4 are underway, and construction equipment can be seen on the plot for Building 5. Extensive solar panel arrays have been built out.
113 MW2 operating
Estimate: all five AI buildings operational. The mean time from first ground activity to operational across buildings 1 and 2 was 25.6 (25.1 and 26.0 months). Buildings 3 and 4 have been underway since Mar 2026, and building 5's plot only has construction equipment as of Jul 2026, so +25 months gives Aug 2028 as campus completion. Company guidance is faster: capacity "expected to double to 600MW by the end of 2027" per Kenanga via The Star; JDC4 phases Sep-25/Sep-26/Sep-27 per MIDF. The resulting ~429MW IT independently matches Kenanga's "expected IT load of 430MW" for the 600MW park (Kenanga, 9 Dec 2024).
284 MW5 operating
Adopt a site
Watch YTL Johor
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Official YTL page for the campus
- YTL press release on the use of GB200's
- Aerial footage including the campus
- Epoch AI, "AI data centers", the record for YTL Johor (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
Questions
YTL Johor, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is YTL Johor?
YTL Johor is in Kulai, Johor, Malaysia, at YTL Green Data Centers, Kulai, Johor, Malaysia. Epoch AI publishes its coordinates as 1.6183, 103.5192.
Who owns YTL Johor?
Epoch AI does not name an owner yet.
How much power does YTL Johor use?
Epoch AI estimates its IT power at 113 MW as of July 13, 2026, and its total facility power at 155 MW. It projects 284 MW of IT power by August 1, 2028.
Is YTL Johor operating?
Yes, and it is growing. Epoch AI counts 2 buildings operating as of July 13, 2026, with more capacity on its timeline.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).