Power Map · Operating, expanding

Nscale Keflavik, Reykjanesbær

Nscale Keflavik is an SI data center in Reykjanesbær, Suðurnes, Iceland, owned by Nscale. Epoch AI estimates its IT power at 5.1 MW as of July 27, 2026, with 1 building operating, and projects 10.2 MW by December 31, 2026. Its public timeline starts on July 8, 2022.

IT power
5.1 MWJul 27, 2026
Facility power
6.6 MW
Status
Operating, expanding
Buildings operating
1

Where it is

The site and its facts

Nscale Keflavik on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Reykjanesbær, Suðurnes, IcelandOpen in OpenStreetMap
Place
Reykjanesbær, Suðurnes, Iceland
Address
Valhallarbraut 868, 262 Reykjanesbær, Iceland
Coordinates
63.9762° N, 22.5764° W
Owner
Nscale
Chips
B300
Compute
About 5,821 H100 equivalentsEpoch AI estimate, Jul 27, 2026
Projected
10.2 MW IT power by December 31, 2026Epoch AI projection, not a fact yet

Heat Watch

Nscale Keflavik: heat seen from space

Over the last three summers NASA's MODIS read the ground here +0.6 °C against the land 5 to 10 km around it by day.

Lights On

Nscale Keflavik: light at night

NASA's night imagery read 42.8 of 100 over this site in October 2026, against 39.3 in October 2018, the first month read. Against a year before: +4.8 points. Light is not proof of what runs inside.

Timeline

Dated, from the public record

Epoch AI's dated notes on Nscale Keflavik, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

  1. Site preparation begins for the southernmost KEF301 data center, here labeled as Building 1. Heilbrigðiseftirlit Suðurnesja records authorization for Mannverk to demolish the existing structure at Valhallarbraut 872, the parcel later identified as KEF301.

    No IT power yet0 operating

  2. Construction of Building 1 begins. Reykjanesbær planning records from May 11 explicitly state that the next construction phase of KEF301 was under construction by May 2023, so we model it as starting by the beginning of the month as a conservative estimate.

    No IT power yet0 operating

  3. Nscale's GPU fit-out begins at the datacenter owned by Verne in Keflavik, Iceland. Estimated from Verne's statement that the first 7.5 MW deployment was completed in approximately three months; the exact start date was not disclosed.

    No IT power yet0 operating

  4. First Nscale AI capacity operational. Verne reports the first 7.5 MW of Nscale capacity deployed with 128 racks, including 64 liquid-cooled NVIDIA GB300 racks. The AI capacity is assumed to be in the southernmost white building because it is the newest major data hall, has roughly 16 MW of capacity, and was the hall still being expanded most recently before Nscale's deployment; however, Verne and Nscale have not publicly confirmed the building assignment. Digital 9 Reykjanesbær

    5.1 MW1 operating

  5. 64-rack NVIDIA GB300 NVL72 cluster confirmed in production. Nscale reports that production benchmarking was performed during June across all 64 racks. Month-end is used because the exact benchmark date was not disclosed.

    5.1 MW1 operating

  6. Building 1 is operational (estimate). Full campus visibly externally complete from satellite imagery. Virtually no active construction visible.

    5.1 MW1 operating

  7. Full 15 MW AI deployment projected operational. Nscale and Verne announced a 15 MW deployment across Verne's Iceland campus during 2026. We're modeling the end of the year as the completion date based on this announcement and the progress visible.

    10.2 MW1 operating

Adopt a site

Watch Nscale Keflavik

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

The watcher

Loading the watcher.

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

  • Approved updates show here with their date.

Sources

Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

Questions

Nscale Keflavik, answered

Where it is, who owns it and how much power it uses, from the public record.

Where is Nscale Keflavik?

Nscale Keflavik is in Reykjanesbær, Suðurnes, Iceland, at Valhallarbraut 868, 262 Reykjanesbær, Iceland. Epoch AI publishes its coordinates as 63.9762, -22.5764.

Who owns Nscale Keflavik?

Epoch AI lists Nscale as its owner.

How much power does Nscale Keflavik use?

Epoch AI estimates its IT power at 5.1 MW as of July 27, 2026, and its total facility power at 6.6 MW. It projects 10.2 MW of IT power by December 31, 2026.

Is Nscale Keflavik operating?

Yes, and it is growing. Epoch AI counts 1 building operating as of July 27, 2026, with more capacity on its timeline.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).