Power Map · Under construction

EcoDataCenter 2, Borlänge

EcoDataCenter 2 is an SI data center in Borlänge, Dalarna County, Sweden, owned by Mistral AI and used by Mistral AI. Epoch AI tracks it as under construction: no building is operating yet as of August 17, 2026, and projects 48 MW by June 30, 2028. Its public timeline starts on September 1, 2025.

IT power
Not statedEpoch AI
Facility power
Not stated
Status
Under construction
Buildings operating
0

Where it is

The site and its facts

EcoDataCenter 2 on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.

Borlänge, Dalarna County, SwedenOpen in OpenStreetMap
Place
Borlänge, Dalarna County, Sweden
Address
Kvarnsvedsvägen 420, 784 66 Borlänge, Sweden
Coordinates
60.5263° N, 15.4170° E
Owner
Mistral AI
Users
Mistral AI
Projected
48 MW IT power by June 30, 2028Epoch AI projection, not a fact yet

The Gigawatt Ledger · Under construction

EcoDataCenter 2, Borlänge: announced against built

No power figure was announced for this project. Epoch AI tracks the site as under construction, with no building operating as of August 17, 2026.

Heat Watch

EcoDataCenter 2: heat seen from space

Over the last three summers NASA's MODIS read the ground here +0.1 °C against the land 5 to 10 km around it by day.

Lights On

EcoDataCenter 2: light at night

NASA's night imagery read 12.3 of 100 over this site in October 2026, against 15.1 in October 2018, the first month read. Against a year before: +0.5 points. Light is not proof of what runs inside.

Timeline

Dated, from the public record

Epoch AI's dated notes on EcoDataCenter 2, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.

  1. Land clearing begins. EcoDataCenter announces on September 24th that construction has started on EcoDataCenter 2, so we model it as started from the beginning of the month.

    No IT power yet0 operating

  2. Buildings 1 and 2 still under construction. The first two building shells are visibly well into construction, with lots of additional ground work visible all across the campus. Based on high-resolution satellite imagery from this date.

    No IT power yet0 operating

  3. Buildings 1 and 2 look fully roofed, with active construction showing cooling and power equipment still being installed. Buildings 3-4 look like their foundations have been laid out and are early in construction.

    No IT power yet0 operating

  4. Buildings 1-2 operational. Based on Bravida stating that installation work in two EcoDataCenter data centers in Borlänge is expected to be completed by mid-2027, together with EcoDataCenter Annual Report 2025 identifying B1 and B2 as the first two buildings under construction.

    24 MW2 operating

  5. Buildings 3-4 operational. Based on Bravida stating that installation work in another EcoDataCenter data center continues through Q1 2028, combined with permit documentation showing four data center buildings under construction by May 2026.

    48 MW4 operating

Adopt a site

Watch EcoDataCenter 2

One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.

The watcher

Loading the watcher.

Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.

Approved updates · 0

  • Approved updates show here with their date.

Sources

Where the facts come from

The sources Epoch AI lists for this site, and the record itself.

Questions

EcoDataCenter 2, answered

Where it is, who owns it and how much power it uses, from the public record.

Where is EcoDataCenter 2?

EcoDataCenter 2 is in Borlänge, Dalarna County, Sweden, at Kvarnsvedsvägen 420, 784 66 Borlänge, Sweden. Epoch AI publishes its coordinates as 60.5263, 15.4170.

Who owns EcoDataCenter 2?

Epoch AI lists Mistral AI as its owner and Mistral AI as its user.

How much power does EcoDataCenter 2 use?

No building is operating yet, so Epoch AI states no IT power for it today. It projects 48 MW of IT power by June 30, 2028.

Is EcoDataCenter 2 operating?

Not yet. Epoch AI tracks it as under construction, with no building operating on its latest entry.

Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).