Gigawatt Ledger · Delayed

Barber Lake, announced against built

Barber Lake is an SI compute project in Colorado City, Texas, by Fluidstack, Cipher Mining and Anthropic. The announced figure is 207 MW of critical IT load (168 MW and 39 MW), from Cipher Mining (Nov 20, 2025). Cipher said it expected to deliver 168 MW of critical IT load by September 2026. Epoch AI's entry of July 30, 2026 reads "still under construction and not yet energized", and Epoch AI estimates the first phase for about December 2026, "about 3 months later than the disclosed target". Its state today: delayed.

Announced
207 MW
Energized
NoneJul 30, 2026
State
Delayed
Source links
4

Announced

What was said, and when

Each row is one public announcement about Barber Lake: who said it, the power or capacity it states in its own unit, the promised date, and the link. Company claims are quoted as claims.

  1. Company statement

    Cipher Mining

    Cipher Mining Signs 168 MW, 10-Year AI Hosting Agreement with Fluidstack

    Cipher signs a 10-year hosting agreement with Fluidstack, backed by Google, at its Barber Lake site.

    “Cipher will deliver 168 MW of critical IT load, supported by a maximum of 244 MW of gross capacity”
    “Expected Delivery of 168 MW of Critical IT Load by September of 2026”
    Power or capacity stated
    168 MW of critical IT load (244 MW gross)
    Promised
    Delivered by September 2026
  2. Company statement

    Anthropic

    Anthropic invests $50 billion in American AI infrastructure

    Anthropic announces data centers with Fluidstack in Texas and New York. It names no site and states no power figure.

    “a $50 billion investment in American computing infrastructure”
    “with sites coming online throughout 2026”
    Power or capacity stated
    None stated
    Promised
    Sites online throughout 2026
  3. Company statement

    Cipher Mining

    Cipher Mining Signs Additional 56 MW, 10-Year AI Hosting Agreement with Fluidstack

    Fluidstack takes the rest of the site.

    “an additional 39 MW of critical IT load”
    “lease the entire 300 MW of capacity at Cipher's Barber Lake site”
    “Expected Delivery of Additional 39 MW of Critical IT Load at Barber Lake by January 2027”
    Power or capacity stated
    39 MW more critical IT load; the whole 300 MW site
    Promised
    Delivered by January 2027

Built

What public evidence confirms

What is on the ground today, from the Power Map data and from any statement or filing that states live power.

Delayed

Cipher said it expected to deliver 168 MW of critical IT load by September 2026. Epoch AI's entry of July 30, 2026 reads "still under construction and not yet energized", and Epoch AI estimates the first phase for about December 2026, "about 3 months later than the disclosed target".

  1. Epoch AI estimate

    Epoch AI · Power Map

    Anthropic Barber Lake on the Power Map

    Epoch AI tracks Anthropic Barber Lake as under construction: no building is operating as of July 30, 2026.

    Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north. Most of the 120 backup diesel generators are also in place. Substantial progress since Nov 2025, still under construction and not yet energized.
    IT power running
    None
    Whole facility
    None

    Epoch AI projects 207 MW of IT power by April 30, 2027. A projection, not a fact yet.

Heat Watch

Anthropic Barber Lake: heat seen from space

Over the last three summers NASA's MODIS read the ground here +0.5 °C against the land 5 to 10 km around it by day.

Timeline

Announcements and evidence, by date

What was promised and what was seen, in the order it became public. The full dated record of each site is on its Power Map page.

  1. Anthropic Barber Lake: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map

  2. Cipher Mining: 168 MW of critical IT load (244 MW gross). Promised: delivered by September 2026.Announcement · GlobeNewswire

  3. Anthropic: no power figure stated. Promised: sites online throughout 2026.Announcement · Anthropic

  4. Cipher Mining: 39 MW more critical IT load; the whole 300 MW site. Promised: delivered by January 2027.Announcement · GlobeNewswire

  5. Anthropic Barber Lake: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map

  6. Anthropic Barber Lake: 0 buildings operating, no IT power yet.Evidence · Epoch AI, on the Power Map

Corrections

See something wrong? File a correction

Sign in with your SI Passport and say what is wrong, with a link to a public source. The team reads the source before anything changes, and approved corrections stay on this page.

File a correction

Sign in with your SI Passport to file a correction. It is a free message signature and never moves tokens.

A correction needs a link. Nothing shows until the team approves it. If your Passport carries an Org check it shows here, and an organization correcting its own project is labeled as such.

Corrections on file · 0

  • Loading the corrections on file.

Sources

Every link behind this page

Read on November 11, 2026. An undated page carries the date it was read.