- Colossus 1 gas turbines
Onsite Power Watch · Gas
Colossus 1 gas turbines
Colossus 1 gas turbines: 15 Solar SMT-130 gas turbines, up to 247 MW. It serves xAI's Colossus 1 data center, Memphis, Tennessee. Status: permitted, as of July 2, 2025. Air permit from the Shelby County Health Department, issued July 2, 2025, for 15 turbines.
- Size
- up to 247 MW
- Fuel
- Gas
- Status
- Permitted
- As of
- Jul 2, 2025
The facts
What the public record shows
On site, behind the meter or beside the campus. Each fact below names its source.
- The Shelby County Health Department issued the permit on July 2, 2025, for 15 Solar SMT-130 turbines with up to 247 MW (TechCrunch, July 3, 2025).
- Epoch AI's record of the site, which the Power Map uses, lists the July 2025 turbine permit among its sources.
The filing
The permit or filing behind it
The regulator's decision or the owner's filing that the status rests on.
Permitted · Jul 2, 2025
Air permit from the Shelby County Health Department, issued July 2, 2025, for 15 turbines.
The site
The data center it serves
Linked to the Power Map only where a source ties the two.
Sources
Where every fact comes from
Each source was opened and read on November 23, 2026.
Jul 3, 2025, read Nov 23, 2026
TechCrunch
xAI gets permits for 15 natural gas generators at Memphis data center
retrieved Nov 10, 2026
Epoch AI
The Power Map's site list, towns, status and power come from Epoch AI's open data set of data centers, licensed CC BY 4.0.
Keep going
The grid around it
The same place, other records.
The Queue: Southeast
How much power data centers are asking Southeast for.
See the queueOnsite Power Watch
Every plant built to run a data center directly.
Every plantGrid Watch
Live demand on the grids that host the most sites.
Watch the gridsGigawatt Ledger
What was announced against what is confirmed energized.
Read the LedgerQuestions
Colossus 1 gas turbines, answered
The plant, its status and the sources.
What is Colossus 1 gas turbines?
15 Solar SMT-130 gas turbines, up to 247 MW, built to serve xAI's Colossus 1 data center, Memphis, Tennessee. On site, behind the meter or beside the campus.
What is its status?
Permitted, as of July 2, 2025: Air permit from the Shelby County Health Department, issued July 2, 2025, for 15 turbines.
Where do the facts come from?
From the sources listed on this page, each opened and read on November 23, 2026. The Shelby County Health Department issued the permit on July 2, 2025, for 15 Solar SMT-130 turbines with up to 247 MW (TechCrunch, July 3, 2025).
Join the takeover
Watch the plants with us
Found a newer permit or filing for this plant? Bring it to the $SIS Telegram with its link.