Onsite Power Watch · Nuclear
Susquehanna nuclear plant, Amazon agreement
Susquehanna nuclear plant, Amazon agreement: existing nuclear plant; power purchase agreement, 1,920 MW under the agreement. It serves Amazon's data center campus beside the Susquehanna plant, Pennsylvania. Status: running, as of June 11, 2025. Talen Energy's announcement of June 11, 2025: a power purchase agreement through 2042.
- Size
- 1,920 MW
- Fuel
- Nuclear
- Status
- Running
- As of
- Jun 11, 2025
The facts
What the public record shows
An existing or restarting nuclear plant under an agreement. Each fact below names its source.
- Talen will supply 1,920 MW of nuclear power from Susquehanna to Amazon through 2042, ramping to the full amount no later than 2032 (Talen Energy, June 11, 2025).
- The earlier co-located arrangement moves to front of the meter after transmission work expected in spring 2026: the plant supplies the PJM grid and Talen is Amazon's retail supplier.
- Epoch AI's record of AWS Berwick, which the Power Map uses, cites Talen's sale of the Susquehanna data center campus to AWS.
The filing
The permit or filing behind it
The regulator's decision or the owner's filing that the status rests on.
Running · Jun 11, 2025
Talen Energy's announcement of June 11, 2025: a power purchase agreement through 2042.
The site
The data center it serves
Linked to the Power Map only where a source ties the two.
Sources
Where every fact comes from
Each source was opened and read on November 23, 2026.
Jun 11, 2025, read Nov 23, 2026
Talen Energy
Talen Energy Expands Nuclear Energy Relationship with Amazon
retrieved Nov 10, 2026
Epoch AI
The Power Map's site list, towns, status and power come from Epoch AI's open data set of data centers, licensed CC BY 4.0.
Keep going
The grid around it
The same place, other records.
The Queue: PJM
How much power data centers are asking PJM for.
See the queueOnsite Power Watch
Every plant built to run a data center directly.
Every plantGrid Watch
Live demand on the grids that host the most sites.
Watch the gridsGigawatt Ledger
What was announced against what is confirmed energized.
Read the LedgerQuestions
Susquehanna nuclear plant, Amazon agreement, answered
The plant, its status and the sources.
What is Susquehanna nuclear plant, Amazon agreement?
Existing nuclear plant; power purchase agreement, 1,920 MW under the agreement, built to serve Amazon's data center campus beside the Susquehanna plant, Pennsylvania. An existing or restarting nuclear plant under an agreement.
What is its status?
Running, as of June 11, 2025: Talen Energy's announcement of June 11, 2025: a power purchase agreement through 2042.
Where do the facts come from?
From the sources listed on this page, each opened and read on November 23, 2026. Talen will supply 1,920 MW of nuclear power from Susquehanna to Amazon through 2042, ramping to the full amount no later than 2032 (Talen Energy, June 11, 2025).