1. Home
  2. Onsite Power Watch
  3. Susquehanna nuclear plant, Amazon agreement

Onsite Power Watch · Nuclear

Susquehanna nuclear plant, Amazon agreement

Susquehanna nuclear plant, Amazon agreement: existing nuclear plant; power purchase agreement, 1,920 MW under the agreement. It serves Amazon's data center campus beside the Susquehanna plant, Pennsylvania. Status: running, as of June 11, 2025. Talen Energy's announcement of June 11, 2025: a power purchase agreement through 2042.

Status
Running

The facts

What the public record shows

An existing or restarting nuclear plant under an agreement. Each fact below names its source.

  • Talen will supply 1,920 MW of nuclear power from Susquehanna to Amazon through 2042, ramping to the full amount no later than 2032 (Talen Energy, June 11, 2025).
  • The earlier co-located arrangement moves to front of the meter after transmission work expected in spring 2026: the plant supplies the PJM grid and Talen is Amazon's retail supplier.
  • Epoch AI's record of AWS Berwick, which the Power Map uses, cites Talen's sale of the Susquehanna data center campus to AWS.

The filing

The permit or filing behind it

The regulator's decision or the owner's filing that the status rests on.

Running · Jun 11, 2025

Talen Energy's announcement of June 11, 2025: a power purchase agreement through 2042.

Open the filing

The site

The data center it serves

Linked to the Power Map only where a source ties the two.

Sources

Where every fact comes from

Each source was opened and read on November 23, 2026.

  • Jun 11, 2025, read Nov 23, 2026

    Talen Energy

    Talen Energy Expands Nuclear Energy Relationship with Amazon

    Open the source

  • retrieved Nov 10, 2026

    Epoch AI

    The Power Map's site list, towns, status and power come from Epoch AI's open data set of data centers, licensed CC BY 4.0.

    Open the source

Questions

Susquehanna nuclear plant, Amazon agreement, answered

The plant, its status and the sources.

What is Susquehanna nuclear plant, Amazon agreement?

Existing nuclear plant; power purchase agreement, 1,920 MW under the agreement, built to serve Amazon's data center campus beside the Susquehanna plant, Pennsylvania. An existing or restarting nuclear plant under an agreement.

What is its status?

Running, as of June 11, 2025: Talen Energy's announcement of June 11, 2025: a power purchase agreement through 2042.

Where do the facts come from?

From the sources listed on this page, each opened and read on November 23, 2026. Talen will supply 1,920 MW of nuclear power from Susquehanna to Amazon through 2042, ramping to the full amount no later than 2032 (Talen Energy, June 11, 2025).

Join the takeover

Watch the plants with us

Found a newer permit or filing for this plant? Bring it to the $SIS Telegram with its link.