Power Map · Operating, expanding
CoreWeave Denton TX, Denton
CoreWeave Denton TX is an SI data center in Denton, Texas, United States, owned by CoreWeave and used by OpenAI (Epoch AI rates this likely). Epoch AI estimates its IT power at 262 MW as of September 1, 2026, with 7 buildings operating, and projects 282 MW by May 31, 2027. Its public timeline starts on November 1, 2024.
- IT power
- 262 MWSep 1, 2026
- Facility power
- 367 MW
- Status
- Operating, expanding
- Buildings operating
- 7
Where it is
The site and its facts
CoreWeave Denton TX on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- Denton, Texas, United States
- Address
- 8171 Jim Christal Rd, Denton, TX 76207
- Coordinates
- 33.2148° N, 97.2100° W
- Owner
- CoreWeave
- Users
- OpenAI (Epoch AI rates this likely)
- Chips
- B200
- Compute
- About 252,653 H100 equivalentsEpoch AI estimate, Sep 1, 2026
- Projected
- 282 MW IT power by May 31, 2027Epoch AI projection, not a fact yet
The Gigawatt Ledger · Energized
Denton: announced against built
260 MW was announced for this project. Public evidence puts 262 MW in operation as of September 1, 2026, against 260 MW announced: 100%. The announcement states IT load, so it is set against the IT load running.
Heat Watch
CoreWeave Denton TX: heat seen from space
Over the last three summers NASA's MODIS read the ground here -0.7 °C against the land 5 to 10 km around it by day, a change of +0.3 °C since before work on this build began.
Lights On
CoreWeave Denton TX: light at night
NASA's night imagery read 38.2 of 100 over this site in October 2026, against 12.9 in October 2018, the first month read. Against a year before: -4.7 points. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on CoreWeave Denton TX, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
Construction start - The Texas Department of Licensing and Regulation reports Core Scientific is converting existing Bitcoin mining buildings into AI data centers, planning to build AROUND the existing Denton Energy Center.
No IT power yet0 operating
First 8 MW billable tranche dedicated to AI starts running at the site, with another 40 scheduled by the end of the quarter.
8 MW1 operating
Half the campus energized. 67 billable MW are now dedicated to CoreWeave's GPUs across three buildings.
67 MW3 operating
Buildings 1-3 (Denton North) are largely built out/operational, and Denton South has its first data hall plus support equipment substantially installed. Remaining Denton South buildings (4-7) still under construction. This is according to satellite imagery.
131 MW4 operating
Buildings 1-3 (Denton North) are fully operational running AI (Denton North at 90 MW, Denton South partially running at 41). This is according to an earnings call from this date.
131 MW4 operating
Buildings 1-7 are operational and running, with no construction work visible. This is based on both satellite imagery, and the Q2 2026 Earnings call stating the campus was operational by midyear 2026.
262 MW7 operating
Building 8 interior fit-out scheduled to begin. TDLR project TABS2026028247 schedules a $110M interior fit-out of the existing 27,678.22 sq ft Building A as a data hall beginning September 1, 2026.
262 MW7 operating
Building 8 projected operational. TDLR project TABS2026028247 schedules Building A's data-hall fit-out for completion by this date.
282 MW8 operating
Adopt a site
Watch CoreWeave Denton TX
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Core Scientific - CoreWeave Announce 1.2B expansion in Denton, TX
- Core Scientific - Denton Datacenter Official Site
- TMF - Core Scientific Q4 2025 Earnings Transcript
- WSJ - plans to rent to OpenAI
- Epoch AI, "AI data centers", the record for CoreWeave Denton TX (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
Questions
CoreWeave Denton TX, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is CoreWeave Denton TX?
CoreWeave Denton TX is in Denton, Texas, United States, at 8171 Jim Christal Rd, Denton, TX 76207. Epoch AI publishes its coordinates as 33.2148, -97.2100.
Who owns CoreWeave Denton TX?
Epoch AI lists CoreWeave as its owner and OpenAI (Epoch AI rates this likely) as its user.
How much power does CoreWeave Denton TX use?
Epoch AI estimates its IT power at 262 MW as of September 1, 2026, and its total facility power at 367 MW. It projects 282 MW of IT power by May 31, 2027.
Is CoreWeave Denton TX operating?
Yes, and it is growing. Epoch AI counts 7 buildings operating as of September 1, 2026, with more capacity on its timeline.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).