Power Map · Operating, expanding
Coreweave Helios, Afton
Coreweave Helios is an SI data center in Afton, Texas, United States, owned by CoreWeave and used by OpenAI (Epoch AI rates this speculative). Epoch AI estimates its IT power at 132 MW as of August 30, 2026, with 1 building operating, and projects 528 MW by January 1, 2029. Its public timeline starts on May 31, 2025.
- IT power
- 132 MWAug 30, 2026
- Facility power
- 200 MW
- Status
- Operating, expanding
- Buildings operating
- 1
Where it is
The site and its facts
Coreweave Helios on the map, with every fact Epoch AI publishes for it. Orange dots are the nearest SI data centers.
- Place
- Afton, Texas, United States
- Address
- 984 County Road 112, Afton, TX 79220
- Coordinates
- 33.7751° N, 100.8698° W
- Owner
- CoreWeave
- Users
- OpenAI (Epoch AI rates this speculative)
- Chips
- B200
- Compute
- About 159,552 H100 equivalentsEpoch AI estimate, Aug 30, 2026
- Projected
- 528 MW IT power by January 1, 2029Epoch AI projection, not a fact yet
Heat Watch
Coreweave Helios: heat seen from space
Over the last three summers NASA's MODIS read the ground here -0.5 °C against the land 5 to 10 km around it by day.
Lights On
Coreweave Helios: light at night
NASA's night imagery read 33.1 of 100 over this site in October 2026, against 0.4 in October 2018, the first month read. Against a year before: +12.0 points. Light is not proof of what runs inside.
Timeline
Dated, from the public record
Epoch AI's dated notes on Coreweave Helios, quoted as Epoch AI wrote them, with its IT power estimate on each date. Projections are marked.
The former crypto mining Helios site begins converting the first building and expanding, with land cleared for additional buildings.
No IT power yet0 operating
Backup generator pads and steel framing for chillers are visible, similar to the 3D renderings.
No IT power yet0 operating
Building 1 appears substantially complete. The main white-roofed data hall is visible with exterior mechanical/electrical equipment rows installed on both sides, and adjacent generator/equipment pads plus laydown yards are active. A large graded pad north of Building 1 suggests preparation for the next phase/building. No clear satellite evidence that the AI/HPC facility is operational yet.
No IT power yet0 operating
Building 1 appears externally complete and likely Ready for Service, with all cooling/roofing/generators in place, but we're not labeling it operational yet due to visible surrounding yard/construction work. CoreWeave likely still needs time to install chips and use all their designated chip capacity. The pad to the northeast has foundations being laid out for Building 2.
No IT power yet0 operating
Building 1 operational at full capacity. This is based on "Phase I", which is expected to be operational by the end of the first half of 2026. We added two months of overhead to account for remaining construction and/or installation of CoreWeave's chips, since the June 17 image still showed active minor construction around the building.
132 MW1 operating
Building 2 and 3 are operational at full capacity. This corresponds to "Phase II", which is expected to be delivered "throughout 2027". We assume it takes until the end of 2027 to reach full capacity.
396 MW3 operating
Building 4 operational at full capacity. This corresponds to "Phase III", which is expected to be delivered "starting in 2028". We assume it takes until the end of 2028 to reach full capacity.
528 MW4 operating
Adopt a site
Watch Coreweave Helios
One SI Passport holder can be this site's named watcher and file dated updates. Nothing a watcher files shows until the team approves it.
The watcher
Loading the watcher.
Signing in is a free message signature. It never moves tokens. Photos are made fresh on the server without their metadata, and show only once the team approves them.
Approved updates · 0
- Approved updates show here with their date.
Sources
Where the facts come from
The sources Epoch AI lists for this site, and the record itself.
- Galaxy Q3 financial results with power capacity timeline
- Permit review with details on backup generators and power capacity
- 3D renderings of Helios Building 1 on Galaxy's website, showing generators and chillers
- TDLR record with Building 1 construction costs and end date
- Epoch AI, "AI data centers", the record for Coreweave Helios (CC BY 4.0), retrieved November 10, 2026
Nearby
The nearest SI data centers
The four closest sites on the Power Map, as the crow flies.
144 km away
Goodnight
Claude, Texas, United States
IT power not stated
153 km away
Anthropic Barber Lake
Colorado City, Texas, United States
IT power not stated
174 km away
OpenAI Stargate Abilene
Abilene, Texas, United States
824 MW IT power
175 km away
Crusoe Abilene Expansion
Abilene, Texas, United States
IT power not stated
Questions
Coreweave Helios, answered
Where it is, who owns it and how much power it uses, from the public record.
Where is Coreweave Helios?
Coreweave Helios is in Afton, Texas, United States, at 984 County Road 112, Afton, TX 79220. Epoch AI publishes its coordinates as 33.7751, -100.8698.
Who owns Coreweave Helios?
Epoch AI lists CoreWeave as its owner and OpenAI (Epoch AI rates this speculative) as its user.
How much power does Coreweave Helios use?
Epoch AI estimates its IT power at 132 MW as of August 30, 2026, and its total facility power at 200 MW. It projects 528 MW of IT power by January 1, 2029.
Is Coreweave Helios operating?
Yes, and it is growing. Epoch AI counts 1 building operating as of August 30, 2026, with more capacity on its timeline.
Data center facts: Epoch AI, "AI data centers", CC BY 4.0, retrieved November 10, 2026. Map: Natural Earth (public domain).