ERCOT counts every request from a load of 75 MW or more at one point of interconnection. Its count grew from 63 GW in December 2024 to about 474 GW in June 2026, most of it data centers. In July 2026 the old process closed and a one time batch study took over, with a narrower count of its own.
- Figures on file
- 12
- Newest figure
- Nov 5, 2026
- Power Map sites inside
- 14
- Live on Grid Watch
- Yes
Over time
Where the source repeats
Each line joins one measure from one source at the dates the source gave, and nothing else. Every number keeps its own definition, date and source. Figures with different definitions are never added together, and a chart joins only the same measure from the same source.
- Large load interconnection requests, GW, each dot a date the source gave
Every figure
ERCOT, figure by figure
Newest first. Each card opens its source document.
Asked for
about 166 GW
as of November 5, 2026
Requested by the 245 large loads in the community impact survey
Requested interconnection capacity of the 245 large loads (75 MW or more) that answered ERCOT's data center state and community impact survey. Preliminary as of November 5, 2026.
ERCOT: Data Center State and Community Impact RFI: Preliminary Summary, PUC Open Meeting, Nov 5, 2026
In study
127.9 GW
as of September 3, 2026
Batch Zero, conditional studied load
158 projects that met the qualifications to be conditionally included as studied load, as of September 3, 2026. Final inclusion follows ERCOT's verification and audit, due by December 10, 2026.
ERCOT: Item 14: Batch Zero Update, Board of Directors, September 14 to 15, 2026, Sep 11, 2026
In study
66.4 GW
as of September 3, 2026
Batch Zero, conditional base load
204 projects that met the qualifications to be conditionally included as base load, in the classification ERCOT sent on September 3, 2026. A different group from the studied load below: the two are never added here.
ERCOT: Item 14: Batch Zero Update, Board of Directors, September 14 to 15, 2026, Sep 11, 2026
In study
about 205 GW
as of July 28, 2026
Eligible for the Batch Zero study
Large load eligible for inclusion in Batch Zero, ERCOT's one time study under Senate Bill 6, based on existing studies. Preliminary, as of July 28, 2026.
ERCOT: ERCOT update to the Texas House Committee on State Affairs, August 19, 2026, Aug 19, 2026
Asked for
about 474 GW
as of June 2026
Large load interconnection requests
Large loads seeking interconnection, as of June 2026. ERCOT says about 90% are data centers. This is the last count of the old process, which ended on July 10, 2026.
ERCOT: ERCOT update to the Texas Senate, July 29, 2026: Assessing the grid, Jul 29, 2026
Asked for
438 GW
as of the board deck of May 24, 2026
Large load interconnection requests
Requests tracked through the PGRR 115 based process, as stated in the deck for the June 1 to 2, 2026 board meeting. The deck gives no separate as of date. ERCOT notes the vast majority have no studies submitted.
ERCOT: Item 8: Interconnection and Grid Analysis Update, Board of Directors, June 1 to 2, 2026, May 24, 2026
Asked for
about 410 GW
as of March 26, 2026
Large load interconnection requests
Large loads seeking interconnection, as of March 26, 2026. ERCOT says about 87% are data centers and that the count rose 178 GW since the end of 2025.
ERCOT: Item 9: Interconnection and Grid Analysis Update, Board of Directors, Apr 13, 2026
Approved
8,876 MW
as of February 25, 2026
Approved to energize
Megawatts that had received approval to energize, in ERCOT's status update of February 25, 2026.
ERCOT: Large Load Interconnection Status Update to the Technical Advisory Committee, Feb 25, 2026
Asked for
about 226 GW
as of November 18, 2025
Large load interconnection requests
Large loads seeking interconnection, as of November 18, 2025. ERCOT adds that about 128,000 MW of these had not yet submitted planning studies for review.
ERCOT: ERCOT Monthly, November 2025: Large Load Interconnection Requests Update, Dec 19, 2025
Running
about 5.3 GW
as of November 18, 2025
Observed energized
Large loads approved to energize that ERCOT observed operating, as of November 18, 2025.
ERCOT: ERCOT Monthly, November 2025: Large Load Interconnection Requests Update, Dec 19, 2025
Approved
about 7.5 GW
as of November 18, 2025
Approved to energize
Large loads ERCOT had approved to energize, as of November 18, 2025: about 5,300 MW observed energized plus about 2,200 MW approved but not yet operating, in ERCOT's own split.
ERCOT: ERCOT Monthly, November 2025: Large Load Interconnection Requests Update, Dec 19, 2025
Asked for
63 GW
as of December 2024
Large load interconnection requests
Loads of 75 MW or more seeking interconnection to the ERCOT system, as ERCOT tracks them. ERCOT gives this December 2024 figure for reference in its November 2025 update.
ERCOT: ERCOT Monthly, November 2025: Large Load Interconnection Requests Update, Dec 19, 2025
On August 3, 2026, after a directive from the Governor, ERCOT paused approvals to energize data centers and crypto facilities of 75 MW or more while it verifies and audits the loads in Batch Zero (ERCOT, Item 14, September 2026).
| Figure | Amount | Stage | As of | Source |
|---|---|---|---|---|
| Requested by the 245 large loads in the community impact survey | about 166 GW | Asked for | November 5, 2026 | ERCOT |
| Batch Zero, conditional studied load | 127.9 GW | In study | September 3, 2026 | ERCOT |
| Batch Zero, conditional base load | 66.4 GW | In study | September 3, 2026 | ERCOT |
| Eligible for the Batch Zero study | about 205 GW | In study | July 28, 2026 | ERCOT |
| Large load interconnection requests | about 474 GW | Asked for | June 2026 | ERCOT |
| Large load interconnection requests | 438 GW | Asked for | the board deck of May 24, 2026 | ERCOT |
| Large load interconnection requests | about 410 GW | Asked for | March 26, 2026 | ERCOT |
| Approved to energize | 8,876 MW | Approved | February 25, 2026 | ERCOT |
| Large load interconnection requests | about 226 GW | Asked for | November 18, 2025 | ERCOT |
| Observed energized | about 5.3 GW | Running | November 18, 2025 | ERCOT |
| Approved to energize | about 7.5 GW | Approved | November 18, 2025 | ERCOT |
| Large load interconnection requests | 63 GW | Asked for | December 2024 | ERCOT |
Utilities
The utilities in this grid
A utility's own count of the load it has agreed to serve, from its own filings.
American Electric Power (AEP)
AEP reports, each quarter, the new load backed by signed customer agreements across its companies in PJM, SPP and ERCOT. The count went from 24 GW in July 2025 to 69 GW through 2030 in July 2026, and to 84 GW by 2031 in October 2026. AEP's figure covers all of its companies; it is not split by grid except where AEP says so.
- New load by 2030 under customer agreements, GW, each dot a date the source gave
Under contract
84 GW
as of October 28, 2026
Contracted load by 2031
After 15 GW of new load commitments in the third quarter of 2026. AEP moved the horizon to 2031, so this figure is kept off the 2030 line.
AEP: Third-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1), Oct 28, 2026
Under contract
69 GW
as of July 30, 2026
Contracted load growth through 2030
After 6 GW more of signed load agreements in the second quarter of 2026, mainly in Texas.
AEP: Second-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1), Jul 30, 2026
Under contract
63 GW
as of May 5, 2026
New load by 2030 under signed agreements
After 7 GW of new load agreements signed in the first quarter of 2026. AEP Texas accounts for 41 GW of the commitments.
AEP: First-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1), May 5, 2026
Under contract
56 GW
as of February 12, 2026
New load by 2030 under signed agreements
Incremental load by 2030, all backed by signed agreements. AEP Texas alone rose from 13 GW to 36 GW, backed by signed letters of agreement.
AEP: Fourth-quarter and full-year 2025 earnings release (SEC Form 8-K, exhibit 99.1), Feb 12, 2026
Under contract
28 GW
as of October 29, 2025
New load by 2030 under customer agreements
Load additions by 2030 backed by electric service agreements or letters of agreement, supported by an additional 190 GW of load requests.
AEP: Third-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1), Oct 29, 2025
Under contract
24 GW
as of July 30, 2025
New load by 2030 under customer agreements
Incremental load by 2030 under customer agreements with firm financial commitments, mainly in Indiana, Ohio and Texas. AEP also cited more than 190 GW of load requests at various stages.
AEP: Second-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1), Jul 30, 2025
On the Power Map
SI data centers inside ERCOT
Each card opens the site on the Power Map. Status and power are Epoch AI's, read November 10, 2026.
The Power MapOperating
OpenAI Stargate Abilene
Abilene, Texas
824 MW of IT power
As of Nov 1, 2026, Epoch AI
On the Power MapOperating, expanding
CoreWeave Denton TX
Denton, Texas
262 MW of IT power
As of Sep 1, 2026, Epoch AI
On the Power MapOperating
Meta Temple
Temple, Texas
178 MW of IT power
As of Sep 30, 2026, Epoch AI
On the Power MapOperating, expanding
Coreweave Helios
Afton, Texas
132 MW of IT power
As of Aug 30, 2026, Epoch AI
On the Power MapOperating
Google Midlothian
Midlothian, Texas
103 MW of IT power
As of Jul 1, 2026, Epoch AI
On the Power MapOperating, expanding
Google Red Oak
Red Oak, Texas
77 MW of IT power
As of Feb 6, 2026, Epoch AI
On the Power MapOperating
Microsoft SAT40
San Antonio, Texas
75 MW of IT power
As of Feb 4, 2026, Epoch AI
On the Power MapOperating
Microsoft SAT14
San Antonio, Texas
47 MW of IT power
As of Mar 31, 2026, Epoch AI
On the Power MapOperating, expanding
Vantage TX1
San Antonio, Texas
32 MW of IT power
As of Feb 15, 2026, Epoch AI
On the Power MapUnder construction
Anthropic Barber Lake
Colorado City, Texas
No building running yet
As of Jul 30, 2026, Epoch AI
On the Power MapUnder construction
Crusoe Abilene Expansion
Abilene, Texas
No building running yet
As of Jan 15, 2026, Epoch AI
On the Power MapUnder construction
Goodnight
Claude, Texas
No building running yet
On the map inside: ERCOT, SPP
As of Apr 16, 2026, Epoch AI
On the Power MapUnder construction
OpenAI Stargate Milam
Burlington, Texas
No building running yet
On the map inside: ERCOT, MISO
As of Mar 23, 2026, Epoch AI
On the Power MapUnder construction
OpenAI Stargate Shackelford
Abilene, Texas
No building running yet
As of Sep 4, 2026, Epoch AI
On the Power Map14 Power Map sites fall inside this grid's area on the federal Control Areas map (HIFLD Open, year 2018 boundaries). 2 of them sit where the map draws two areas over the same spot; they are listed under each. A site's place on that map is a guide, not proof of which utility serves it.
Sources
Where every figure comes from
Each source was opened and read on November 23, 2026.
validated May 15, 2020, read Nov 23, 2026
U.S. Department of Homeland Security, HIFLD Open (public copy)
Control Areas (balancing authority areas), sourced from FERC 714, EIA 860 and EIA 861, year 2018
Jul 30, 2025, read Nov 23, 2026
AEP
Second-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)
Oct 29, 2025, read Nov 23, 2026
AEP
Third-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)
Dec 19, 2025, read Nov 23, 2026
ERCOT
ERCOT Monthly, November 2025: Large Load Interconnection Requests Update
Feb 12, 2026, read Nov 23, 2026
AEP
Fourth-quarter and full-year 2025 earnings release (SEC Form 8-K, exhibit 99.1)
Feb 25, 2026, read Nov 23, 2026
ERCOT
Large Load Interconnection Status Update to the Technical Advisory Committee
Apr 13, 2026, read Nov 23, 2026
ERCOT
Item 9: Interconnection and Grid Analysis Update, Board of Directors
May 5, 2026, read Nov 23, 2026
AEP
First-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)
May 24, 2026, read Nov 23, 2026
ERCOT
Item 8: Interconnection and Grid Analysis Update, Board of Directors, June 1 to 2, 2026
Jul 29, 2026, read Nov 23, 2026
ERCOT
ERCOT update to the Texas Senate, July 29, 2026: Assessing the grid
Jul 30, 2026, read Nov 23, 2026
AEP
Second-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)
Aug 19, 2026, read Nov 23, 2026
ERCOT
ERCOT update to the Texas House Committee on State Affairs, August 19, 2026
Sep 11, 2026, read Nov 23, 2026
ERCOT
Item 14: Batch Zero Update, Board of Directors, September 14 to 15, 2026
Oct 28, 2026, read Nov 23, 2026
AEP
Third-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)
Nov 5, 2026, read Nov 23, 2026
ERCOT
Data Center State and Community Impact RFI: Preliminary Summary, PUC Open Meeting
retrieved Nov 10, 2026
Epoch AI
The Power Map's site list, towns, status and power come from Epoch AI's open data set of data centers, licensed CC BY 4.0.
Keep going
The same grid, other records
Every page of the set reads a different public record.
Power Map
Every SI data center public data can confirm, with its power.
Open the mapGigawatt Ledger
What was announced against what is confirmed energized.
Read the LedgerOnsite Power Watch
The plants built to run data centers directly.
See the plantsGrid Watch
Live demand on the grids that host the most sites.
Watch the gridsBill Watch
Home power prices in every state with a site.
Read the billQuestions
ERCOT, answered
The figures, the stages and the limits.
How much power are data centers asking ERCOT for?
ERCOT counts every request from a load of 75 MW or more at one point of interconnection. Its count grew from 63 GW in December 2024 to about 474 GW in June 2026, most of it data centers. In July 2026 the old process closed and a one time batch study took over, with a narrower count of its own. Each figure on this page has its own definition and date; figures with different definitions are never added together.
Is all of that going to be built?
No figure here says what will be built. Requests are what customers asked for; many requests are speculative, duplicated across grids or withdrawn. The stages on this page (asked for, in study, approved, under contract, running) are the source's own words.
Which data centers are inside ERCOT?
The Power Map lists 14 sites inside ERCOT's area on the federal Control Areas map. See the list below; each links to its page.
Where do the figures come from?
From the grid operator's own board decks, filings and reports and the utilities' own filings with the SEC, each read on November 23, 2026. The links are on every figure.
How hard is ERCOT running right now?
Grid Watch shows ERCOT's demand hour by hour from the EIA, against its own forecast and its record.
Join the takeover
Read the queue with us
Open a source, check a figure yourself and bring what you find to the $SIS Telegram.