The Queue · SPP
The queue at SPP
SPP studies large loads through its High Impact Large Load (HILL) process. The only count found for this page is SPP's own for Missouri: 11 requests for 3,871 MW, of which 568 MW had reached a service agreement by August 2026. SPP wide totals are on the monthly recheck list.
- Figures on file
- 2
- Newest figure
- Aug 19, 2026
- Power Map sites inside
- 10
- Live on Grid Watch
- Yes
Over time
Where the source repeats
This grid has no measure that its source repeats three times yet, so there is no line. Every number keeps its own definition, date and source. Figures with different definitions are never added together, and a chart joins only the same measure from the same source.
The figures below are each a single reading. A line appears here once the same source gives the same measure three times.
Every figure
SPP, figure by figure
Newest first. Each card opens its source document.
Approved
568 MW
as of August 19, 2026
Added to a service agreement, Missouri
Two of those requests, added to a service agreement. Another 725 MW (five requests) was in study and 2,578 MW (four requests) potential or pending study.
SPP: SPP Status Update to the Missouri Public Service Commission, Aug 19, 2026
Asked for
3,871 MW
as of August 19, 2026
HILL requests in Missouri
Total load of the 11 High Impact Large Load requests in SPP's Missouri area (7 in one path, 4 in the other). Missouri only, not all of SPP.
SPP: SPP Status Update to the Missouri Public Service Commission, Aug 19, 2026
SPP's own Missouri detail lists 650 MW of the requests as data center load and 1,968 MW as load whose use was not disclosed.
Utilities
The utilities in this grid
A utility's own count of the load it has agreed to serve, from its own filings.
American Electric Power (AEP)
AEP reports, each quarter, the new load backed by signed customer agreements across its companies in PJM, SPP and ERCOT. The count went from 24 GW in July 2025 to 69 GW through 2030 in July 2026, and to 84 GW by 2031 in October 2026. AEP's figure covers all of its companies; it is not split by grid except where AEP says so.
- New load by 2030 under customer agreements, GW, each dot a date the source gave
Under contract
84 GW
as of October 28, 2026
Contracted load by 2031
After 15 GW of new load commitments in the third quarter of 2026. AEP moved the horizon to 2031, so this figure is kept off the 2030 line.
AEP: Third-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1), Oct 28, 2026
Under contract
69 GW
as of July 30, 2026
Contracted load growth through 2030
After 6 GW more of signed load agreements in the second quarter of 2026, mainly in Texas.
AEP: Second-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1), Jul 30, 2026
Under contract
63 GW
as of May 5, 2026
New load by 2030 under signed agreements
After 7 GW of new load agreements signed in the first quarter of 2026. AEP Texas accounts for 41 GW of the commitments.
AEP: First-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1), May 5, 2026
Under contract
56 GW
as of February 12, 2026
New load by 2030 under signed agreements
Incremental load by 2030, all backed by signed agreements. AEP Texas alone rose from 13 GW to 36 GW, backed by signed letters of agreement.
AEP: Fourth-quarter and full-year 2025 earnings release (SEC Form 8-K, exhibit 99.1), Feb 12, 2026
Under contract
28 GW
as of October 29, 2025
New load by 2030 under customer agreements
Load additions by 2030 backed by electric service agreements or letters of agreement, supported by an additional 190 GW of load requests.
AEP: Third-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1), Oct 29, 2025
Under contract
24 GW
as of July 30, 2025
New load by 2030 under customer agreements
Incremental load by 2030 under customer agreements with firm financial commitments, mainly in Indiana, Ohio and Texas. AEP also cited more than 190 GW of load requests at various stages.
AEP: Second-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1), Jul 30, 2025
On the Power Map
SI data centers inside SPP
Each card opens the site on the Power Map. Status and power are Epoch AI's, read November 10, 2026.
The Power MapOperating
Google Pryor (North)
Pryor, Oklahoma
368 MW of IT power
As of Sep 6, 2026, Epoch AI
On the Power MapOperating
Google Council Bluffs (East)
Council Bluffs, Iowa
237 MW of IT power
On the map inside: MISO, SPP
As of Jul 7, 2026, Epoch AI
On the Power MapOperating, expanding
Google Omaha
Omaha, Nebraska
237 MW of IT power
As of Jun 30, 2026, Epoch AI
On the Power MapOperating
Google Papillion
Papillion, Nebraska
237 MW of IT power
As of May 4, 2026, Epoch AI
On the Power MapOperating, expanding
Google Lincoln
Lincoln, Nebraska
141 MW of IT power
As of May 12, 2026, Epoch AI
On the Power MapOperating
Google Kansas City East
Kansas City, Missouri
105 MW of IT power
As of Aug 1, 2026, Epoch AI
On the Power MapOperating
Meta Sarpy
Springfield, Nebraska
80 MW of IT power
As of Aug 2, 2026, Epoch AI
On the Power MapOperating, expanding
CoreWeave Ellendale ND
Ellendale, North Dakota
68 MW of IT power
On the map inside: MISO, SPP
As of Jun 30, 2026, Epoch AI
On the Power MapUnder construction
CoreWeave Muskogee OK
Muskogee, Oklahoma
No building running yet
On the map inside: Associated Electric Cooperative, SPP
As of Jun 13, 2026, Epoch AI
On the Power MapUnder construction
Goodnight
Claude, Texas
No building running yet
On the map inside: ERCOT, SPP
As of Apr 16, 2026, Epoch AI
On the Power Map10 Power Map sites fall inside this grid's area on the federal Control Areas map (HIFLD Open, year 2018 boundaries). 4 of them sit where the map draws two areas over the same spot; they are listed under each. A site's place on that map is a guide, not proof of which utility serves it.
Sources
Where every figure comes from
Each source was opened and read on November 23, 2026.
validated May 15, 2020, read Nov 23, 2026
U.S. Department of Homeland Security, HIFLD Open (public copy)
Control Areas (balancing authority areas), sourced from FERC 714, EIA 860 and EIA 861, year 2018
Jul 30, 2025, read Nov 23, 2026
AEP
Second-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)
Oct 29, 2025, read Nov 23, 2026
AEP
Third-quarter 2025 earnings release (SEC Form 8-K, exhibit 99.1)
Feb 12, 2026, read Nov 23, 2026
AEP
Fourth-quarter and full-year 2025 earnings release (SEC Form 8-K, exhibit 99.1)
May 5, 2026, read Nov 23, 2026
AEP
First-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)
Jul 30, 2026, read Nov 23, 2026
AEP
Second-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)
Aug 19, 2026, read Nov 23, 2026
SPP
SPP Status Update to the Missouri Public Service Commission
Oct 28, 2026, read Nov 23, 2026
AEP
Third-quarter 2026 earnings release (SEC Form 8-K, exhibit 99.1)
retrieved Nov 10, 2026
Epoch AI
The Power Map's site list, towns, status and power come from Epoch AI's open data set of data centers, licensed CC BY 4.0.
Keep going
The same grid, other records
Every page of the set reads a different public record.
Power Map
Every SI data center public data can confirm, with its power.
Open the mapGigawatt Ledger
What was announced against what is confirmed energized.
Read the LedgerOnsite Power Watch
The plants built to run data centers directly.
See the plantsGrid Watch
Live demand on the grids that host the most sites.
Watch the gridsBill Watch
Home power prices in every state with a site.
Read the billQuestions
SPP, answered
The figures, the stages and the limits.
How much power are data centers asking SPP for?
SPP studies large loads through its High Impact Large Load (HILL) process. The only count found for this page is SPP's own for Missouri: 11 requests for 3,871 MW, of which 568 MW had reached a service agreement by August 2026. SPP wide totals are on the monthly recheck list. Each figure on this page has its own definition and date; figures with different definitions are never added together.
Is all of that going to be built?
No figure here says what will be built. Requests are what customers asked for; many requests are speculative, duplicated across grids or withdrawn. The stages on this page (asked for, in study, approved, under contract, running) are the source's own words.
Which data centers are inside SPP?
The Power Map lists 10 sites inside SPP's area on the federal Control Areas map. See the list below; each links to its page.
Where do the figures come from?
From the grid operator's own board decks, filings and reports and the utilities' own filings with the SEC, each read on November 23, 2026. The links are on every figure.
How hard is SPP running right now?
Grid Watch shows SPP's demand hour by hour from the EIA, against its own forecast and its record.